Legislation Details

File #: 26-5189    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/23/2026 In control: Commissioners Court
On agenda: 8/6/2026 Final action: 8/6/2026
Title: Request for approval of a change in contract with SER Construction Partners LLC, in connection with Treaschwig Rd A (Phase 2) - from west of Cypress Creek to 1,000' east of Birnam Wood Blvd - 2014, with an addition in the amount of $84,516.06, Job No. 25/0216, UPIN 23103MF2TA01, Precinct 3, MWBE Contracted Goal: 36.09%, MWBE Current Participation: 40.62%.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 25/0216, UPIN 23103MF2TA01

Vendor/Entity Legal Name (if applicable): SER Construction Partners, LLC

 

MWBE Contracted Goal (if applicable): 36.09%

MWBE Current Participation (if applicable): 40.62%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with SER Construction Partners LLC, in connection with Treaschwig Rd A (Phase 2) - from west of Cypress Creek to 1,000' east of Birnam Wood Blvd - 2014, with an addition in the amount of $84,516.06, Job No. 25/0216, UPIN 23103MF2TA01, Precinct 3, MWBE Contracted Goal: 36.09%, MWBE Current Participation: 40.62%.

end

 

Background and Discussion:

This project consists of the reconstruction and widening of Treaschwig Road (Phase 2) from west of Whittaker Way to East of Birnam Wood Boulevard.  The scope includes drainage improvements, construction of a new bridge over the creek, traffic signal installation, striping, and all other miscellaneous safety enhancements required.

 

This change in Contract includes:

(PCO #2, RFI #2) While reviewing the TCP for Phases 3 and 4, safety concerns were noted at the ends of the SSCB runs due to blunt-end conditions and no crash protection being shown.  To address this, it is recommended to install two Crash Cushion Attenuators (CCA) during Phase 3. In Phase 4, the SSCB will be replaced with LPCB, and the same two CCAs can remain in place, so no additional units will be needed.

Cost Impact: $8,221.66.

 

(PCO #3, RFI #15) It was noted that temporary drainage installed in phase 1 will be conflicting with 84" RCP. The temporary drainage will be removed and will require to install a new temporary inlet with RCP to maintain positive drainage.  This added work has been reviewed and accepted by the Precinct, EOR, and OCE.

Cost Impact: $4,574.40

 

(PCO #4, RFI #19) RFI #19 addressed the proposed headwall at the 36" sewer crossing (Sta. 195+96 RT).  The original plans did not provide sufficient headwall height to achieve the required 3:1 slope to the top of curb.  The Engineer of Record issued revised drawings extending the headwall to meet design requirements.  This revision resulted in an overrun of approximately 9.81 CY under the existing line item, with an associated cost of $21,473.11.

 

(PCO #5, RFI #13) The change order covers removal of an existing 8-inch waterline at STA 189+45 that was field-identified as asbestos concrete (AC), requiring specialized handling not included in the original contract.  This work is necessary to clear a conflict with the proposed 84-inch RCP and avoid delays.  The additional cost for AC pipe removal was submitted by SER Construction and approved by HCWCID 136, EOR, Precinct, and HCD. Cost impact $12,520.33

 

(PCO #6, RFI #25) At station 188+93, proposed 36" storm PP conflicted with existing gravity 12" sanitary sewer line. Due to very limited space, the proposed and accepted resolution per contractor, EOR, and HCED, was to utilize arch pipe.  This proposal has been reviewed and accepted by the precinct. Cost impact $8,409.47

 

(PCO #7, RFI #24) For the 18-inch force main at STA-186+22 RT sheet 47/270, and STA-200+07 LT sheet 53/270, the plans specify the installation of the force main.  However, they do not indicate whether it will be connected to or tied into the existing line and no pay item exists for this work.  Contractor provided a proposal for a connection which was reviewed and approved by EOR & Precinct. Cost impact $29,317.09

 

Expected Impact:

These changes are necessary to address field conflicts, safety concerns, and design clarifications encountered during construction. The work will maintain project progress and improve safety and constructability, with no anticipated impact to the overall project scope.

 

Alternative Options:

None at this time.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

 

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/26/2025

454 (25-5498)

Contract Award

02/12/2026

24 (26-0865)

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources:

 

Existing Budget

 

 

 

 

1070 - Mobility Fund                3002

$

$84,516.06

$84,516.06

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$84,516.06

$84,516.06

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$84,516.06

$84,516.06

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 8/6/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B