Legislation Details

File #: 25-0508    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 1/9/2025 In control: Commissioners Court
On agenda: 1/23/2025 Final action: 1/23/2025
Title: Request for approval of the Final Investment Memo for the Plumbing Systems Repair and Replacement project (continuous) for an additional incremental authorization of $13,895,000 for a total FY2025 authorization of $15,295,000.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP,  CFM, ENV-SP

Managing Department: County Engineer

Managing Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP,  CFM, ENV-SP

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Plumbing Systems Repair and Replacement Countywide

Project ID (if applicable): MF0Z6

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $13,895,000

Total Estimated Project Cost: $15,295,000

 

Request Summary:

title

Request for approval of the Final Investment Memo for the Plumbing Systems Repair and Replacement project (continuous) for an additional incremental authorization of $13,895,000 for a total FY2025 authorization of $15,295,000.

end

 

Project Description:

These funds are intended to support new construction in the coming fiscal year and the continuous lifecycle management and resiliency upgrades for county facilities. The projects will identify and address all required upgrades and enhancements of plumbing systems in County facilities that are currently maintained by the Office of County Engineer. This includes sewer systems, domestic water supply, fire safety systems, pumps, improving existing equipment with safer more reliable materials, and installing more efficient fixtures. These projects will ensure the county facilities plumbing infrastructure is updated, resilient, and functional to ensure support to county residents through the years and upcoming disaster seasons.

Below are the planned allocations; there might be changes in the County’s needs that result in minor operational changes for the projects throughout the Fiscal Year, but the overall scope will remain the same, and any additional authorization would go through Commissioners Court approval.

 

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

1010 Lamar - Storm and Sanitary Drain Pipe Replacement

$1,600K

FY 2026

1010 Lamar - Domestic Water Tank Replacement

$1,200K

FY 2026

1010 Lamar - Design and Long Lead Items Building Re-Coring

$5,500K

FY 2026

1111 Fannin - Fire Water Pump Replacements

$490K

FY 2026

1302 Preston (Annex 2) - Plumbing Upgrades

$2,110K

FY 2026

1200 Congress (Annex 50)  - Replacement of Sub-Slab Sanitary Sewer Lines/Domestic Water

$300K

FY 2026

701 West Baker, Baytown (Annex 8) - Architectural and MEP Upgrades Design Only

$350K

FY 2025

701 W Baker Rd, Baytown (Annex 8)   - HVAC/Controls Upgrades

$50K

FY 2025

Downtown Central Plants Major Connecting Pipe - Redesign

$500K

FY 2026

701 San Jacinto Jail - Domestic Water Mezzanine Tank Refurbishment

$1,200K

FY 2025

Contingency - Countywide

$1,995K

FY 2026

Total FY 2025 Projects

$15,295k

 

Unencumbered Current Balance

$(1,400K)

 

Total

$13,895k

 

 

Justification & Alternatives:

This program seeks to construct critical plumbing repairs and improvements throughout county facilities that will significantly address health and safety of building tenants (Sanitary, Fire Water and Domestic Water Projects), energy efficiencies (Central Plan Connecting Pipe , 1010 Lamar building Re-Coring, higher efficient pipes and Fixtures in all projects), and resiliency of county facilities (All projects will upgrade the existing plumbing infrastructure nearly 30-50 years old to current significantly more resilient standards).

Failure to maintain, modernize and upgrade the County's existing facilities will result in significantly more expensive deferred maintenance, future inflation costs, closure of certain areas, non-code compliance, and, most importantly, risks to life/safety. Plumbing systems are critical and or required to support the building infrastructure and to allow occupancy. Domestic supply and wastewater capacity is a building code requirement. Running water and flushing toilets are required to maintain the functionality of a facility; without this critical infrastructure, a facility will be shut down. Savings would be a challenge to calculate because failures are unpredictable. If the facilities are not updated, the severely degraded plumbing will continue to fail effecting the resiliency of facilities and ability of county staff to use those facilities for normal operations or disaster recovery operations.

Not funding this program would lead to an even greater backlog of deferred maintenance to perform later and, in some cases, could create hazards to life and safety.  Delay in project timeline may increase costs due to increased deterioration of infrastructure, potential bid increases, and increase in material and labor costs.

 

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  1. Make Harris County safer and more just.

County Strategic Plan Objective: C: Improve safety and health conditions in the jail.

Justice/Safety Initiative (Goal 1):  C1: Support the Jail and Community Safety Infrastructure Governance Advisory Committee’s and Resident Advisory Committee’s efforts to increase non-carceral options and improve safety, security, and other conditions in jail facilities.

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): T2: Make County buildings more energy efficient.

Housing Initiative (Goal 6): N/A


Decision Analysis Matrix Score (rubric on last page): 13

Previous Court Action:

8/28/2018

1.o.7

Approved: $500K authorization

9/11/2018

3.f.3

Approved: $500K CP allocation

6/4/2019

CIP

Approved: $2M authorization per Interim CIP

7/9/2019

3.f.5

Approved: $2M CP allocation

12/17/2019

4.i.11

Approved: $1M CP allocation

1/7/2020

II.1.d

Approved: $2M authorization per FY20 CIP

7/14/2020

4.h.6

Approved: $1M CP allocation

3/9/2021

88

Approved: Harris County - Proposed Capital Improvements Program; Facility and Maintenance Projects: Plumbing Systems Repair and Replacement Countywide, pages 281 and 291 ($2,428,570 authorization for FY21-22)

8/24/2021

94

Approved: $1,928,570 incremental authorization reduction; $2,245,000 CP reduction

3/8/2022

113

Approved: Request for approval of a Final Investment Memo for the Plumbing Systems Repair and Replacement Countywide project for an additional $912,000 for a SFY 22 authorization of $1,415,000 for Facilities and Property Maintenance and request for approval of commercial paper funding for Engineering for the project in the additional amount of $495,000 for a total of $2,750,000. (p.13)

10/18/2022

127

Approved: Request for approval of a Final Investment Memo for the Plumbing Systems Repair and Replacement Countywide project for an additional $1,646,000 fora FY 2023 authorization of $2,662,000. 22-6664

8/29/2023

23-4874 <https://harriscountytx.legistar.com/LegislationDetail.aspx?ID=6325968&GUID=B1597E3E-E64E-4B3B-B9CE-57FD154F8A09&Options=ID%7CText%7C&Search=Plumbing&FullText=1>Approved: Request for approval of a Final Investment Memo for the Plumbing Systems Repair and Replacement Countywide project for an additional $516,000 for a total FY24 authorization of $2,683,000.

 

 

Address: Multiple

Precinct(s): Countywide

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/23/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Legal funding compliance confirmed by: Paige Abernathy, Assistant County Attorney, 7/30/2024

Department Approval by: Ross Hosket, P.E., CFM, ENV-SP, Director - Building Operations Services, Office of the County Engineer

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 1/7/2025

________________________________________

Commercial Paper Request (For OMB use only):

Receiving Department: N/A

Project PeopleSoft ID: N/A

CP Series Description: N/A

OMB Financial Management contact: N/ADecision Analysis Matrix scoring tool - Commissioners Court has approved the rubric below for scoring capital projects. Please complete the last two rows for OMB review.

Scoring option

Strategic Plan alignment (3x weighting)

Evidence base

Impact on outcomes

Cost effectiveness

Ease of implementation

Collaboration / partnerships

Environmental sustainability

Equity

Total

-1

Antithetical to one or more aspects of the Strategic Plan

Evidence shows net negative impact on the intended goal

Impact is clearly negative

Costs expected (or shown) to outweigh benefits

County has no/limited existing capabilities and dependencies are likely to impede

Could negatively impact relationships with partners

Negatively impacts environment and/or climate change mitigation efforts

Inequitable

n/a

0

Does not align to a Strategic Objective

Evidence base is not well defined or measurable

Size of impact on one or more strategic outcomes is negligible or unclear

Net comparison is unclear

County has no/limited existing capabilities or dependencies are likely to impede

Does not involve collaboration with partners

Net neutral impact on environment and/or climate change mitigation efforts

Does not consider equity to a meaningful degree

n/a

1

Aligns to a Strategic Objective but not to a Strategic Initiative

Limited evidence-based research on outcomes; may have qualitative/theoretical support

Outcomes are defined but without target levels and/or expected impact is moderate

Moderate direct/indirect benefit relative to costs

County has existing capability to implement or dependencies are unlikely to impede

Moderately expands County leverage through collaboration with partner(s)

Marginally positive impact on environment and/or climate change mitigation efforts

Considers equity to a meaningful degree, but not comprehensively

n/a

2

Aligns to a Strategic Objective and a Strategic Initiative

Outcomes are directly supported by evidence base or credible research supports anticipated outcomes

Outcomes are clearly defined and include target levels; expected impact on outcomes is high

Significant direct/indirect benefit relative to costs

County has existing capability to implement and dependencies are unlikely to impede

Significantly expands County leverage through collaboration with partner(s)

Positively impacts environment and/or climate change mitigation efforts

Considers equity meaningfully and comprehensively

n/a

Score         (-1,0,1,2)

6

1

1

1

2

0

2

0

13

Rationale

Objective: Improve safety and health conditions in the jail. Initiative: Support the Jail and Community Safety Infrastructure Governance Advisory Committee’s and Resident Advisory Committee’s efforts to increase non-carceral options and improve safety, security, and other conditions in jail facilities.

Per County Strategic Plan Objective C, it improves safety and health conditions in the jail.   Per Climate/Resilience Initiative Goal 5, it makes County buildings more energy efficient.

Per County Strategic Plan Goal 1, it makes Harris County safer and more just.

Per Climate/Resilience Initiative Goal 5, it makes County buildings more energy efficient and cost effective.

County has existing capability to implement, and dependencies are unlikely to impede.

It does not involve collaboration with partners.

Per Climate/Resilience Initiative Goal 5, it makes County buildings more energy efficient.

Goal not applicable to request.

n/a