Legislation Details

File #: 26-0698    Version: 1 Name:
Type: Grant Status: Passed
File created: 1/15/2026 In control: Commissioners Court
On agenda: 1/29/2026 Final action: 1/29/2026
Title: Request by Housing and Community Development for approval of Amendment #14 to the 2017 Hurricane Harvey CDBG-DR Contract (19-147-002-B490) between Harris County and the Texas General Land Office.

Primary Department: Housing and Community Development

Primary Department Head/Elected Official: Thao Costis

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Grant - Amendment

 

Project ID (if applicable): 19-147-002-B490

Vendor/Entity Legal Name (if applicable): Texas General Land Office

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): 0%

Justification for 0% Grant Indirect Costs Rate (if applicable): Grantor does not allow indirect cost capture

 

Request Summary (Agenda Caption):

title

Request by Housing and Community Development for approval of Amendment #14 to the 2017 Hurricane Harvey CDBG-DR Contract (19-147-002-B490) between Harris County and the Texas General Land Office.

end

 

Background and Discussion:

To increase the CDBG-DR funds from $859,900,679.96 to $880,140,858.39. The $20,240,178.43 funds are added back from the previous amendment. The following attachments were revised: Project Budgets; Performance Statements; Federal Assurance and Certifications; General Affirmations; Nonexclusive List of Applicable Laws, Rules, and Regulations; and GLO Information Security Appendix.

 

Expected Impact:

To provide recovery for areas impacting by Hurricane Harvey in Harris County.

 

Alternative Options:

N/A

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  Choose an item.

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): Choose an item.

Health Initiative (Goal 4): Choose an item.

Climate/Resilience Initiative (Goal 5): Choose an item.

Housing Initiative (Goal 6): W2: Increase stock of permanent supportive housing.

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

5/24/2022

173

8th Amendment to the Agreement between Harris County and the Texas General Land Office to the 2017 Harvey CDBG-DR Contract

2/21/2023

237

9th Amendment to the Agreement between Harris County and the Texas General Land Office to the 2017 Harvey CDBG-DR Contract

10/10/2023

200

10th Amendment to the Agreement between Harris County and the Texas General Land Office to the 2017 Harvey CDBG-DR Contract

3/26/2024

253

11th Amendment to the Agreement between Harris County and the Texas General Land Office to the 2017 Harvey CDBG-DR Contract

8/27/2024

215

12th Amendment to the Agreement between Harris County and the Texas General Land Office to the 2017 Harvey CDBG-DR Contract

2/27/2025

85

13th Amendment to the Agreement between Harris County and the Texas General Land Office to the 2017 Harvey CDBG-DR Contract

 

Location:

Address (if applicable): N/A

Precinct(s): Countywide

 

Fiscal and Personnel Summary

Service Name

2017 Hurricane Harvey CDBG-DR Contract (19-147-002-B490)

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

1

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$20,240,178.43

$20,240,178.43

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 1/29/2026

 

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Disaster Recovery related item

 

Contact(s) name, title, department: Gregory J. Frazier, PFI Investments Director, HCD

 

Attachments (if applicable): Amendment and Court Order