Legislation Details

File #: 24-4766    Version: 1 Name:
Type: Financial Authorization Status: Passed
File created: 7/25/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval to partially release retainage to DivisionOne Construction, LLC, in connection with the Peden Building (Harvey) in the amount of $595,920.54, Job No. 21/0295, UPIN 18035MF0W501, Precinct 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Financial Authorization

 

Project ID (if applicable): 21/0295 - 18035MF0W501

Vendor/Entity Legal Name (if applicable): DivisionOne Construction, LLC

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval to partially release retainage to DivisionOne Construction, LLC, in connection with the Peden Building (Harvey) in the amount of $595,920.54, Job No. 21/0295, UPIN 18035MF0W501, Precinct 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

 

Background and Discussion:

The Peden Building project was substantially completed November 7th, 2023, and DivisionOne Construction LLC, has completed closeouts for the originally contracted work. The only work remaining is the negotiation of outstanding change orders.

 

 

Expected Impact:

This court action would allow the Contractor to bill for a partial amount of the due retainage compensation for work performed and completed.

 

Alternative Options:

Should we not move forward with this action, Retainage will continue to be withheld on contractors for work completed after contractual Substantial Completion has been declared.

 

Alignment with Goal(s):

X Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/9/2021

187

Contract Award

10/11/2022

34

Change in Contract #21/0295-1

12/13/2022

62

Change in Contract #21/0295-2

01/31/2023

38

Change in Contract #21/0295-3

05/16/2023

54

Change in Contract #21/0295-4

08/08/2023

55

Change in Contract #21/0295-5

11/14/2023

32

Change in Contract #21/0295-6

02/27/2024

56

Change in Contract #21/0295-7

05/07/2024

248

Substantial Completion

 

Location:

Address (if applicable): 600 San Jacinto St, Houston, TX 77002

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: August 6th, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Disaster Recovery related item

Contact(s) name, title, department: Dr. Ron Lerner, Director of High Profile Special Projects (Interim), Harris County Engineering Department