File #: 24-0394    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 1/17/2024 In control: Commissioners Court
On agenda: 1/30/2024 Final action: 1/30/2024
Title: Request for approval to execute an Agreement with B2Z Engineering, LLC for construction materials testing program management services for all construction for the Barrier-Free HCTRA Program in two phases, and construction materials testing services and geotechnical engineering services for portions of the Barrier Free HCTRA Program in the amount of $6,900,000 (Countywide). MWDBE Contracted Goal: 18%.
Attachments: 1. 24-0394 - B2Z_-_CMT_AGREEMENT_(Barrier-Free_Program)

Department: Toll Road Authority

Department Head/Elected Official: Roberto Treviño, P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): N/A

Vendor/Entity Legal Name (if applicable): B2Z Engineering, LLC

 

MWDBE Contracted Goal (if applicable): 18%

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval to execute an Agreement with B2Z Engineering, LLC for construction materials testing program management services for all construction for the Barrier-Free HCTRA Program in two phases, and construction materials testing services and geotechnical engineering services for portions of the Barrier Free HCTRA Program in the amount of $6,900,000 (Countywide). MWDBE Contracted Goal: 18%.

end

 

Background and Discussion:

On January 10, 2023, Commissioners Court approved the advertisement for Construction Material Testing (CMT) services for projects related to the Barrier-Free Program.  The selected engineering firms will be responsible for providing CMT services for the Barrier-Free Program.  With Commissioners Court authorization to negotiate, an agreement is being made with B2Z Engineering, LLC. HCTRA anticipates returning to a future court to request addition of funds for second phase of projects.

 

Expected Impact:

Funding for this request will come from the Toll Road Authority.

 

Alternative Options:

No other recommended solutions for this identified need.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

1/10/2023

128

Court approval to advertise for CMT services

8/29/2023

165

Court approval to negotiate an agreement

 

Location:

Address (if applicable): N/A

Precinct(s): Countywide

 

Fiscal and Personnel Summary

Service Name

Tolling Solutions

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$2,300,000

$2,300,000

$2,300,000

Total Incremental Expenditures

$2,300,000

$2,300,000

$2,300,000

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Revenue - TRA

$2,300,000

$2,300,000

$2,300,000

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$2,300,000

$2,300,000

$2,300,000

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$2,300,000

$2,300,000

$2,300,000

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 30, 2024

Anticipated Implementation Date (if different from Court date): Notice to proceed pending approval of Agreement

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority