Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0219
Vendor/Entity Legal Name (if applicable): GMJ Paving Co., LLC
MWDBE Contracted Goal (if applicable): 34%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with GMJ Paving Co., LLC, in connection with final construction of Maintenance - BS2N Cloverleaf 2021, with a deduction in the amount of $990,188.59, Job No. 22/0219-4, UPIN 22102MF2FH01, Precinct 2, MWDBE Contracted Goal: 34%, MWDBE Current Participation: 100%.
end
Background and Discussion:
The project includes the mill and overlay of various roads in the Cloverleaf area for the BetterStreets2Neighborhoods Community Program for Harris County Precinct 2.
Work has been completed in accordance with Harris County standards and specifications. This change in contract allows processing of final pay estimate and close out the project.
Expected Impact:
This action allows for unused funds to be returned to Harris County.
Alternative Options:
Action required to return unused funds.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
08/02/2022 |
226 |
Contract Award |
03/14/2023 |
33 |
Contract Amendment for additional funds and extension of project term |
03/14/2023 |
45 |
Contract Amendment for additional funds |
08/08/2023 |
63 |
Contract Amendment for additional funds and extension of project term |
Location:
Address (if applicable):
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
|
|
FY 24 |
FY 25 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
-$990,188.59 |
$ |
$ |
Total Incremental Expenditures |
-$990,188.59 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Other |
-$990,188.59 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
-$990,188.59 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
-$990,188.59 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: November 14, 2023
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department
Attachments (if applicable): County Auditor’s Form 1258B