File #: 23-6809    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/6/2023 In control: Commissioners Court
On agenda: 11/14/2023 Final action: 11/14/2023
Title: Request for approval of a change in contract with GMJ Paving Co., LLC, in connection with final construction of Maintenance - BS2N Cloverleaf 2021, with a deduction in the amount of $990,188.59, Job No. 22/0219-4, UPIN 22102MF2FH01, Precinct 2, MWDBE Contracted Goal: 34%, MWDBE Current Participation: 100%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0219

Vendor/Entity Legal Name (if applicable): GMJ Paving Co., LLC

MWDBE Contracted Goal (if applicable): 34%

MWDBE Current Participation (if applicable): 100%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with GMJ Paving Co., LLC, in connection with final construction of Maintenance - BS2N Cloverleaf 2021, with a deduction in the amount of $990,188.59, Job No. 22/0219-4, UPIN 22102MF2FH01, Precinct 2, MWDBE Contracted Goal: 34%, MWDBE Current Participation: 100%.

end

 

Background and Discussion:

 

The project includes the mill and overlay of various roads in the Cloverleaf area for the BetterStreets2Neighborhoods Community Program for Harris County Precinct 2.

 

Work has been completed in accordance with Harris County standards and specifications. This change in contract allows processing of final pay estimate and close out the project.

 

Expected Impact:

 

This action allows for unused funds to be returned to Harris County.

 

Alternative Options:

 

Action required to return unused funds.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/02/2022

226

Contract Award

03/14/2023

33

Contract Amendment for additional funds and extension of project term

03/14/2023

45

Contract Amendment for additional funds

08/08/2023

63

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

-$990,188.59

$

$

Total Incremental Expenditures

-$990,188.59

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Other

-$990,188.59

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

-$990,188.59

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

-$990,188.59

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: November 14, 2023

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B