Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 19103MF12J01; Job No:23/0317
Vendor/Entity Legal Name (if applicable): Ward, Getz & Associates, PLLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): 14.3%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a Professional Services Agreement with Ward, Getz & Associates, PLLC (WGA), for Construction Phase Services in the amount of $241,428.26 for Bernadine Estates and Tower Oaks Section 3 Subdivisions Drainage Improvements -2018, UPIN 19103MF12J01, Precinct 3.
end
Background and Discussion: The project is located in northwest Harris County in the White Oak Bayou watershed. Bernadine subdivision improvements consists of roadside ditches that drain into HCFCD channel E132-00-00. The scope and proposed improvements are to regrade roadside ditches, install a storm sewer system under the ditches, upsize culverts, and reconstruct roadways within the neighborhood. A detention pond will be constructed to mitigate within the project limits. Improvements will comply with Harris County standards. This agreement for Construction Phase Services provided by Ward, Getz & Associates, PLLC (WGA), ensures that the project is built in accordance with the Harris County and Harris County Flood Control regulations.
Expected Impact: This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This agreement for Construction Phase Services is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the Bernadine Estates subdivision homeowners, Harris County, and FEMA. The fiscal impact for this project will come from 1080 infrastructure fund with the long-term goal of reducing drainage costs in the future. No impact to project schedule or staffing anticipated.
Alternative Options: If no action is taken, the engineer of record will not be accessible for support through the construction of the project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
7/30/19 |
21.d.10.o |
Approval of Agreement |
1/26/21 |
21.d.15.f |
Approval of Amendment #1 to Agreement |
3/14/23 |
274 |
Approval of Amendment #2 to Agreement |
Location:
Address (if applicable): Bernadine Estates and Tower Oaks Sec 3
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
Professional Services |
|
FY 24 |
FY 25 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$241,428.26 |
$ |
$ |
Total Incremental Expenditures |
$241,428.26 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
1080 - Infrastructure Fund |
$241,428.26 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$241,428.26 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$241,428.26 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: November 14, 2023
Anticipated Implementation Date (if different from Court date): November 15, 2023
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Director of Disaster & Resiliency Division, HCED
Attachments (if applicable): Construction Phase Services Agreement