Legislation Details

File #: 25-7538    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/20/2025 In control: Commissioners Court
On agenda: 12/11/2025 Final action: 12/11/2025
Title: Request for approval of a change in contract with Platinum Paving, LLC, in connection with Pedestrian Improvements - Various Locations - 2023, adding 72 calendar days, with an addition in the amount of $19,786.50, Job No. 24/0260-3, UPIN 24208MF33Z01, Precinct 3, MWBE Contracted Goal: 64%, MWBE Current Participation: 30.12%.
Attachments: 1. CIC-24208MF33Z01-Pedestrian Improv-24-0260-3-Platinum Pav-P3-12112025.pdf

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0260, UPIN 24208MF33Z01

Vendor/Entity Legal Name (if applicable): Platinum Paving, LLC

 

MWBE Contracted Goal (if applicable): 64%

MWBE Current Participation (if applicable): 30.12%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Platinum Paving, LLC, in connection with Pedestrian Improvements - Various Locations - 2023, adding 72 calendar days, with an addition in the amount of $19,786.50, Job No. 24/0260-3, UPIN 24208MF33Z01, Precinct 3, MWBE Contracted Goal: 64%, MWBE Current Participation: 30.12%.

end

 

Background and Discussion:

The Pedestrian Improvements - Various Locations project consists of replacing the existing rail with up-to-date railing standard, sidewalk replacement and placing new sidewalk in various locations within Harris County. Major work activities include removal of existing guardrail, removal of handrail, concrete sidewalk, concrete curb ramp, Metal Beam Guardrail Fence with Mow Strip, Pedestrian and Traffic railing replacement to the up-to-date standard in Harris County - Precinct 3.

 

The Changes in contract include:

•                     A new line item is needed to install traffic walls at Pine Forest and Lonesome locations to comply with the traffic safety and to complete the work per the proposed revised plan with an additional cost of $7,470.0 and 30 calendar days.

•                     A new line item is needed to install traffic walls at Pine Forest and Lonesome locations to comply with the traffic safety and to complete the work per the proposed revised plan with an additional cost of $12,316.50 and 42 calendar days.

 

Expected Impact:

The change will allow the contractor to complete the proposed work according to the design plan and complete the project.

 

Alternative Options:

There is no other alternative available except the requested changes will allow the contractor to complete the proposed work according to the design plan and complete the project.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/19/2024

315 (24-5738)

Contract Award

05/22/2025

81 (25-3210)

Contract Amendment #1 for additional funds and extension of project term

 

Location:

Address (if applicable): Various Locations

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$19,786.50

$19,786.50

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$19,786.50

$19,786.50

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$19,786.50

$19,786.50

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 12/11/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B