Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): 20104MF1BG01
Vendor/Entity Legal Name (if applicable): MBCO Engineering, LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by MBCO Engineering, LLC. for Birnam Wood Blvd Segment 1 - from 450' north of Hickory Gate Drive to south of J109-01-01 - 2019, UPIN 20104MF1BG01, Precinct 3.
end
Background and Discussion:
The County seeks to re-design of the roadway extension of Birnam Wood Boulevard, from 450' north of Hickory Gate Drive to south of J109-01-01. The re-design scope includes upgrading the existing roadway from a 2-lane concrete half boulevard section to a 4-lane concrete curb and gutter boulevard with 32' raised median and improved drainage. The Study Report has been finalized and is ready for approval.
Expected Impact:
This action will facilitate the design of the project improve the roadway and drainage conditions within this segment of Birnam Wood Boulevard.
Alternative Options:
If not approved, the project will not be able to proceed with the design recommendations in the Study Report and existing conditions will continue.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_X Transportation
_X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
10/13/2020 |
P.2, 1.g.5 |
Professional Engineering Services agreement approved on court agenda |
09/27/2022 |
#55 |
Contract - Amendment. Request for approval to execute an amendment with MBCO Engineering, LLC in the amount of $68,660.00 to update the scope of work for Professional Engineering Services in connection with Birnam Wood Boulevard Segment 1 - from 450' north of Hickorygate Drive to south of J109-01-01 - 2019, UPIN 20104MF1BG01, Precinct 3. |
Location:
Address (if applicable): Birnam Wood Blvd Segment 1 - from 450' north of Hickorygate Dr to south of J109-01-01
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: February 27, 2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department
Attachments (if applicable): Study Report