File #: 24-6859    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 10/18/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Request by the Office of the Purchasing Agent for approval of an award on the basis of low bid to CE Barker Ltd. in the amount of $21,206,362 for construction of a sanitary sewer system, lift station, and force main for the Westfield Estates Subdivision in Precinct 2, and for the County Clerk to execute any applicable bonds to be received (240313), MWDBE Contracted Goal: 19.82%.

Department: Purchasing

Department Head/Elected Official: Paige McInnis

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 240313

Vendor/Entity Legal Name (if applicable): CE Barker Ltd.

 

MWDBE Contracted Goal (if applicable): 19.82%

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request by the Office of the Purchasing Agent for approval of an award on the basis of low bid to CE Barker Ltd. in the amount of $21,206,362 for construction of a sanitary sewer system, lift station, and force main for the Westfield Estates Subdivision in Precinct 2, and for the County Clerk to execute any applicable bonds to be received (240313), MWDBE Contracted Goal: 19.82%.

end

 

Background and Discussion:

Harris County Engineering Department received American Rescue Plan Act funding for wastewater and water projects. Through a vetting process, the Westfield Estates Sanitary Sewer System project was selected. The scope of work includes sanitary sewer lines, manholes, a lift station, a force main, connections to properties, and abandonment of septic systems. Project brings a public sewer system to an area where residents use septic systems, many of which are failing and can contaminate roadside ditches and public waterways.

 

Expected Impact:

Connect residential properties to the newly installed sanitary sewer system and abandon septic systems to minimize bacteria in the environment.

 

Alternative Options:

Continue the use of aging septic systems that are prone to failure.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

X Public Health

_ Transportation

_ Flooding

X Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/19/2024

405

Transmittal by Purchasing of a project scheduled for advertising

 

Location:

Address (if applicable): Westfield Estates Subdivision

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

2651 - American Rescue Plan 2021

$

$21,206,362.00

$21,206,362.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$21,206,362.00

$21,206,362.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$21,206,362.00

$21,206,362.00

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: October 29, 2024

 

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: COVID-19 related item

 

Contact(s) name, title, department: Cassandra Green P.E., ENV SP, Director of Technical Services Division, Office of the County Engineer; Maria Heinzmann, Senior Buyer, Harris County Purchasing

 

Attachments (if applicable): Award Documents