File #: 24-1404    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 3/12/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval of two Community Development Block Grant Entitlement (CDBG-EN) funded agreements with (1) Harris County Precinct Three for the North Eldridge Parkway Target Area 38 - Jersey LMI Sidewalk project; and (2) Harris County Fresh Water Supply District No. 1-A for the Water Line Replacement Phase 2 project.

Department: Housing and Community Development

Department Head/Elected Official: Thao Costis, Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): C2023-005g, C2023-005b

Vendor/Entity Legal Name (if applicable): Harris County Precinct Two

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval of two Community Development Block Grant Entitlement (CDBG-EN) funded agreements with (1) Harris County Precinct Three for the North Eldridge Parkway Target Area 38 - Jersey LMI Sidewalk project; and (2) Harris County Fresh Water Supply District No. 1-A for the Water Line Replacement Phase 2 project.

end

 

Background and Discussion:

On January 10, 2023 and August 8, 2023, Harris County Commissioners Court approved the PY23 Annual Plan for Entitlement funds, which included a global project that is supported by the above referenced Infrastructure Investments project activities.

 

Scopes for each Project:

HC Pct 3 N. Eldrigde Parkway Target Area 38 - Jersey LMI Sidewalk Project: to construct approximately 15,200 feet of sidewalk along N. Eldridge Pkwy and West Rd. to provide safe pedestrian access to facilities and school within the area. This shall benefit four thousand eighty hundred thirty (4,830) persons, which is (60.30%) are low to moderate income in Precinct Three.

 

HC FWSD 1-A Waterline Replacement Phase 2 Project: to installation of approximately 10,000 linear feet of 8”, 6”, and 4” water lines to serve approximately 150 single family residential homes due to the water distribution system does not meet current standards. The project is located in the Linus area within the service boundary of Harris County Fresh Water Supply District No. 1-A. This shall benefit three thousand nine hundred fifteen (3,915) persons, which is (81.06%) are low to moderate income in Precinct Two.

 

Expected Impact:

To provide funding for infrastructure investments project activities that meet the needs of low-and moderate-income residents in Harris County.  The anticipated fiscal impact to the County of the two agreements is $1,495,872.00 in CDBG-EN funds.

 

Alternative Options:

If the agreements are not approved, then low-and moderate-income households in the Harris County Service area will not benefit from the respective infrastructure investments project activities.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

X Public Health

_ Transportation

_ Flooding

X Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): N/A

Precinct(s): Precincts 2 & 3

 

Fiscal and Personnel Summary

Service Name

Infrastructure Investments

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Grant

$23,972

$321,177

$345,149

$1,150,723

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$23,972

$321,177

$345,149

$1,150,723

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$23,972

$321,177

$345,149

$1,150,723

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 3/26/2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Mike Nguyen, Assistant Director-Infrastructure Investments Housing & Community Development

 

Attachments (if applicable): Subrecipient Agreements