Legislation Details

File #: 24-6083    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/23/2024 In control: Commissioners Court
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Request for approval of a change in contract with Statewide Traffic Signal Co., in connection with final construction of Traffic Signal -North Eldridge Parkway at Fetlock Drive - 2022, adding 118 calendar days, with an addition in the amount of $17,029.28, Job No. 21/0369-1, UPIN 23035MF2NK01, Precinct 3, MWDBE Contracted Goal: 17.50%, MWDBE Current Participation: 15.06%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0369, UPIN 23035MF2NK01

Vendor/Entity Legal Name (if applicable): Statewide Traffic Signal Co.

 

MWDBE Contracted Goal (if applicable): 17.50%

MWDBE Current Participation (if applicable): 15.06%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Statewide Traffic Signal Co., in connection with final construction of Traffic Signal -North Eldridge Parkway at Fetlock Drive - 2022, adding 118 calendar days, with an addition in the amount of $17,029.28, Job No. 21/0369-1, UPIN 23035MF2NK01, Precinct 3, MWDBE Contracted Goal: 17.50%, MWDBE Current Participation: 15.06%.

 

end

Background and Discussion:

The project involves constructing a new traffic signal system with mast arms, pedestrian ramps, and a southbound left turn lane at this three-legged intersection of North Eldridge Parkway at Fetlock Drive in Precinct 3.

Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.

 

-                     PCO - 1 Additional 4 days due to hard freeze. - $0.00 - 4 days

-                     PCO - 2 Additional 7 days for excessive rain and soil too wet to work. - $0.00 - 7 days

-                     PCO - 3 Additional 66 days (for relocation and SOLS approval) due to CenterPoint incorrect transformer voltage. - $0.00 - 66 days

-                     PCO - 4 Additional 40 days and $2,619.65 to compensate the contractor for tree removal for wheelchair ramp construction and tree trimming for signal pole installation and signal visibility, - $2,619.65 - 40 days

-                     PCO - 5 Additional 1 day for missing stakes. - $0.00 - 1 days

-                     PCO- 6 Final adjustment $14,409.63

 

Expected Impact:

Changes allow for addition of new bid items to complete the project in accordance with the original intent of the project and in compliance with precinct requests.

 

Alternative Options:

Revise original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X_ Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/04/2022

22-0084

Contract Award

06/25/2024

24-3607

substantial completion

 

 

Location:

Address (if applicable): North Eldridge Parkway at Fetlock Drive

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$17,029.28

$17,029.28

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$17,029.28

$17,029.28

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$17,029.28

$17,029.28

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date:  October 08, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B