File #: 25-3884    Version: 1 Name:
Type: Proposals/Bids Status: Passed
File created: 6/11/2025 In control: Commissioners Court
On agenda: 6/26/2025 Final action: 6/26/2025
Title: Request for approval to advertise for construction bids for the removal and replacement of traffic signal equipment and related improvements at Canino Rd and West Hardy Toll Road, as part of Barrier-Free HCTRA Program (Precinct 2, MWBE Contracted Goal: 17.75%).

Primary Department: Toll Road Authority

Primary Department Head/Elected Official: Roberto Treviño, P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Proposals/Bids

 

Project ID (if applicable): 25/0164

Vendor/Entity Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): 17.75%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to advertise for construction bids for the removal and replacement of traffic signal equipment and related improvements at Canino Rd and West Hardy Toll Road, as part of Barrier-Free HCTRA Program (Precinct 2, MWBE Contracted Goal: 17.75%).

end

 

Background and Discussion:

The proposed project is located along Hardy Toll Road at the intersection of Canino Rd. and Hardy St.  It connects residents across the Hardy Toll Road, by providing safe and ADA accessible connections that use the existing bridge spanning across the tollway. The proposed improvements, replacing a traffic signal and adding a HAWK beacon at the intersections, will improve safety along the corridor by bringing the intersection to current design standards. The project aligns HCTRA and Harris County’s goal to improve safety and accessibility along HCTRA facilities for all Harris County residents.

 

Expected Impact:

This project aligns with Harris County’s goals of providing a reliable, safe, sustainable, and evolving mobility system that meets the diverse connectivity needs of all Harris County residents. Funding from this project comes from Toll Road Authority.

 

Alternative Options:

No other recommended solution for this identified need.

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  G1: Expand pedestrian and cyclist infrastructure on County-managed roads,

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): Canino Rd & Hardy St

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Tolling Operations

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/26/2025

Anticipated Implementation Date (if different from Court date): 10/15/2025

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority

 

Attachments (if applicable): N/A