File #: 24-5689    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/5/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval of a change in contract with DivisionOne Construction, LLC in connection with the Peden Building (Harvey) project, adding 300 calendar days, with an addition in the amount of $562,846.81, Job No. 21/0295-15, UPIN 18035MF0W501, Precinct 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 21/0295 - 18035MF0W501

Vendor/Entity Legal Name (if applicable): DivisionOne Construction, LLC

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with DivisionOne Construction, LLC in connection with the Peden Building (Harvey) project, adding 300 calendar days, with an addition in the amount of $562,846.81, Job No. 21/0295-15, UPIN 18035MF0W501, Precinct 2, Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

Background and Discussion:

Harris County Peden Building is a complete renovation located at 600 North San Jacinto Street, modernization

of three hydraulic passenger elevators and installation of new floodproofing. This change in contract entails

costs and credits for extension of the project for the General Contractor of 300 days, repairs to roof drains, credits for the elevator lobby and HVAC test and balancing, and a credit for the installation of vinyl graphics.

 

Expected Impact:

This change in contract covers the extension of the project by 10 months that was caused by the delay of delivery of air handling units. These specific air handling units, which the General Contractor requested to change with an alternative that may have shipped earlier, were required by the county to keep with specifications. The credits were for work that were returned to and will be completed by the Harris County Engineering Department’s Special Projects team.

The completion of this change in contract will allow the Engineering Department to close out the project.

Alternative Options:

If this change in contract is not executed, DivisionOne will not be compensated for their additional time spent on this project.

 

Alignment with Goal(s):

X Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/9/2021

187

Contract Award

10/11/2022

34

Change in Contract #21/0295-1

12/13/2022

62

Change in Contract #21/0295-2

01/31/2023

38

Change in Contract #21/0295-3

05/16/2023

54

Change in Contract #21/0295-4

08/08/2023

55

Change in Contract #21/0295-5

11/14/2023

32

Change in Contract #21/0295-6

02/27/2024

56

Change in Contract #21/0295-7

05/07/2024

248

Substantial Completion

08/06/2024

78

Partial Retainage Release Letter

 

Location:

Address (if applicable): 600 San Jacinto St, Houston, TX 77002

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$562,846.81

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$562,846.81

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

 

$

$

Total Funding Request

$

$562,846.81

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: September 19th, 2024

Anticipated Implementation Date (if different from Court date): N/a

Emergency/Disaster Recovery Note: Disaster Recovery related item

 

Contact(s) name, title, department: Dr. Ron Lerner, Director of High Profile Special Projects (Interim), Harris County Engineering Department