Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: County Engineer
Secondary Department Head/Elected Official: Dr. Milton Rahman
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Renewal
Project ID (if applicable): 240158
Vendor/Entity Legal Name (if applicable): DCCM North America, LLC
MWBE Contracted Goal (if applicable): 20%
MWBE Current Participation (if applicable): 15.32%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a renewal option with DCCM North America, LLC for professional architectural and/or engineering services to conduct a transportation master plan for the Office of the County Engineer for the period of December 12, 2026 - December 11, 2027, at no cost to the County (240158), MWBE Contracted Goal: 20%, MWBE Current Participation: 15.32%.
end
Background and Discussion:
The Harris County Transportation Master Plan (HCTMP) is a long-range planning document that serves as a guide for future transportation policies, programs, and projects for all unincorporated Harris County through 2050. The planning project addresses all parts of Harris County’s complex transportation system, including capital, operating, and maintenance activities for all transportation modes. The deliverable for this project is a Transportation Plan with a Major Thoroughfare Plan, an Active Transportation Plan, Vision Zero Action Plan, and Geometric Design Guidelines. This plan is anticipated to be submitted for adoption at the Commissioners Court in December.
The current contract with DCCCM expires on December 12, 2026. This proposed extension will ensure sufficient time for DCCM to finalize the deliverables, final presentation, and invoicing process.
Expected Impact:
The completion of the HCTMP, Vision Zero Action Plan, and revised Geometric Design Guidelines will provide Harris County OCE and Precincts a comprehensive approach to the planning and design of the Harris County transportation network offering safe, multimodal options for all travelers whether they drive, walk, or bike.
Alternative Options:
Without DCCM’s support in finalizing these documents, OCE staff would be entirely responsible for completing the HCTMP documents without support from consultants.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.
Justice/Safety Initiative (Goal 1): Choose an item.
Infrastructure Initiative (Goal 2): F1: Strengthen the County’s commitment to Vision Zero principles and goals.
Economy Initiative (Goal 3): Choose an item.
Health Initiative (Goal 4): Choose an item.
Climate/Resilience Initiative (Goal 5): Choose an item.
Housing Initiative (Goal 6): Choose an item.
Additional notes related to the Strategic Plan:
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
5/7/2024 |
37 |
Update regarding the County Transportation Plan, including the scope of work and a schedule for completion. |
|
7/15/24 |
36 |
Update on the scope and schedule of Harris County Transportation Master Plan. |
|
8/6/2024 |
304 |
Authorization to conduct contract negotiations with DCCM North America, LLC. for professional architectural and/or engineering services to conduct a transportation master Plan. |
|
12/10/2024 |
348 |
Approval of an award to DCCM North America, LLC. |
|
10/13/2025 |
361 |
Approval of one-year renewal option with DCCM North America, LLC. |
|
1/8/2026 |
55 |
Scope amendment to include the review of standards, policies, and guidelines to incorporate Vision Zero principles. |
Location: Countywide
Address (if applicable): N/A
Precinct(s): Countywide
|
Fiscal and Personnel Summary |
|
Service Name |
Harris County Transportation Master Plan (HCTMP) |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources 1070 - Mobility Fund |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
|
|
$ |
|
Total Existing Budget |
$ |
|
|
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
|
|
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 11/12/2026
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Mike Etienne, PhD, Chief of Planning and Development Services, Office of the County Engineer, Nancy Garcia, HC Purchasing
Attachments (if applicable): Letter