Legislation Details

File #: 25-5278    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/14/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Request for approval of a change in contract with Cracon, Inc., in connection with final construction of El Dorado Boulevard, with a deduction in the amount of $159,282.07, Job No. 21/0141-3, UPIN 17102MF0PM01, Precinct 2.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Supplemental RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0141, UPIN 17102MF0PM01

Vendor/Entity Legal Name (if applicable): Cracon, Inc.

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

...title

Request for approval of a change in contract with Cracon, Inc., in connection with final construction of El Dorado Boulevard, with a deduction in the amount of $159,282.07, Job No. 21/0141-3, UPIN 17102MF0PM01, Precinct 2.

...end

 

Background and Discussion:

Project includes installation of storm sewer in line detention, sidewalk/ADA ramps and installation of street light conduits and pull boxes along El Dorado Boulevard from Horsepen Bayou to Clear Lake City Boulevard.  This change in contract includes:

 

PCO#35 - FINAL NUMBER ADJUSTMENT: This change in contract includes the final reconciliation of actual quantities used in construction against the bid quantities. -$159,282.07

 

Expected Impact:

Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated for the work performed

 

Alternative Options:

Continue with the original plan.

 

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06/29/2021

379 (21-2953)

Contract Award

03/08/2022

43 (22-1601)

Contract Amendment #1 for additional funds and extension of project term

08/02/2022

49 (22-4555)

Contract Amendment #2 for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3002

$

-$159,282.07

-$159,282.07

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$159,282.07

-$159,282.07

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$159,282.07

-$159,282.07

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/26/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architecture Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B