File #: 24-0650    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 1/23/2024 In control: Commissioners Court
On agenda: 1/30/2024 Final action: 1/30/2024
Title: Request for approval to execute an agreement with Edminster, Hinshaw, Russ and Associates, Inc. d/b/a EHRA in the amount of $227,839.42 for Professional Engineering Services to provide improvements to Treaschwig Rd A (Phase 1) from 1,000' west of Aldine Westfield Rd to west of Cypress Creek, UPIN 14104MF08X01, Precinct 3, MWDBE Contracted Goal: 9.03%.
Attachments: 1. 24-0650-Consultant-UPIN - 14104MF08X01 -EHRA CPS-24GEN0047

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN - 14104MF08X01

Vendor/Entity Legal Name (if applicable): Edminster, Hinshaw, Russ and Associates, Inc. d/b/a EHRA

 

MWDBE Contracted Goal (if applicable): 9.03%

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Edminster, Hinshaw, Russ and Associates, Inc. d/b/a EHRA in the amount of $227,839.42 for Professional Engineering Services to provide improvements to Treaschwig Rd A (Phase 1) from 1,000' west of Aldine Westfield Rd to west of Cypress Creek, UPIN 14104MF08X01, Precinct 3, MWDBE Contracted Goal: 9.03%.

 

end

 

Background and Discussion:

 

This project includes the installation of 7,728 linear feet of underground drainage utilities, 24,800 linear feet of concrete pavement from the existing two lane asphalt roadway to a four lane concrete boulevard, and traffic signal installation along Treaschwig Road at the intersections of Aldine Westfield and Trilby Way.  Edminster, Hinshaw, Russ and Associates, Inc. d/b/a EHRA will provide construction phase services to support the project in construction.

 

Expected Impact:

 

This agreement will allow the engineer of record to continue to support the project through the construction phase.

 

Alternative Options:

 

If no action is taken, the engineer of record will not be available for support during construction of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any): 

Date

Agenda Item #

Action Taken

1/7/2014

1.f.3

Initial agreement with Edminster, Hinshaw, Russ and Associates, Inc.,

4/10/2018

1.g.6

Amendment #1 Agreement with Edminster, Hinshaw, Russ and Associates, Inc.

12/15/2020

1.f.10

Amendment #2 Agreement with Edminster, Hinshaw, Russ and Associates, Inc.

1/4/2022

22

Amendment #3 Agreement with Edminster, Hinshaw, Russ and Associates, Inc.

11/15/2022

41

Amendment #4 Agreement with Edminster, Hinshaw, Russ and Associates, Inc.

 

Location:

Address (if applicable): Treaschwig Road A (Phase 1)

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Professional Service

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$227,839.42

$

$

Total Incremental Expenditures

$227,839.42

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Other 3109

$227,839.42

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$227,839.42

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$227,839.42

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 30, 2024

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Dr. Hatem Elbastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department

Attachments (if applicable): Contract Documents