Legislation Details

File #: 24-4738    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/25/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Bridge Repair - Brinsap 2020 Package 1 - 2022, with a deduction in the amount of $244,362.30, Job No. 22/0364-2, UPIN 23103MF2NY01, Precinct 3, MWDBE Contracted Goal: 30%, MWDBE Current Participation: 0.99%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0364, UPIN 23103MF2NY01

Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC

 

MWDBE Contracted Goal (if applicable): 30%

MWDBE Current Participation (if applicable): 0.99%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Bridge Repair - Brinsap 2020 Package 1 - 2022, with a deduction in the amount of $244,362.30, Job No. 22/0364-2, UPIN 23103MF2NY01, Precinct 3, MWDBE Contracted Goal: 30%, MWDBE Current Participation: 0.99%.

end

 

Background and Discussion:

The project’s scope includes making erosion repairs and concrete spall repairs per Brinsap reports to various bridges throughout Harris County Precinct 3.


This change in contracts includes:

 

•                     Cost of jacking of sidewalk on Oxted Lane at Pilot Gully. ($13,500.00)

•                     Cost of installation of collar to connect new CMP to old CMP at Cypress Mills Boulevard ($2,000.00)

•                     The final adjustment (reconciliation of actual quantities used in construction against the bid quantities) (-$259,862.30).

 

Expected Impact:

Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated.

 

Alternative Options:

Maintain the original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/13/2022

22-7990

Contract Award

12/05/2023

23-6958

Contract Amendment for additional funds and extensions of project time

 

Location:

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109

$

-$244,362.30

-$244,362.30

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

-$244,362.30

-$244,362.30

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

-$244,362.30

-$244,362.30

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date:  August 06, 2024

Anticipated Implementation Date (if different from Court date): n/a

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B