File #: 24-5828    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 9/6/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval of a Final Investment Memo for the Control Systems Repair and Replacement Countywide project for an incremental authorization of $1,640,000 for a total FY2025 authorization of $2,940,000.
Sponsors: Mony Hossain

Department: County Engineer

Department Head: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Control Systems Repair and Replacement Countywide

Project ID (if applicable): CTRL_SYSTMS

Vendor Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Managing Entity: County Engineer

Incremental Authorization Requested: $1,640,000

Total Estimated Project Cost: $5,000,000 (FY25-FY29)

Request Summary:

title

Request for approval of a Final Investment Memo for the Control Systems Repair and Replacement Countywide project for an incremental authorization of $1,640,000 for a total FY2025 authorization of $2,940,000.

end

 

Project Description:

This is a continuous lifecycle management project to identify and address all required upgrades and replacements of Control systems in County facilities that are currently maintained by Building Operations Services (BOS). The control system upgrades will significantly reduce carbon emissions in alignment with the Harris County Climate Action Plan.

 

 

Project Scope:

Control Systems Upgrade and Replacement Countywide is a Program within BOS’s Capital Improvement Plan for asset/equipment replacement and major upgrade projects. The detailed scope of work for FY25 is listed in the table below.

There might be changes in the County’s needs that result in minor operational changes for the project throughout the fiscal year, but the overall scope will remain the same, and any additional authorization would go through Commissioners Court approval.

The facilities updated last year were on the Unify BAS system. The facilities currently being updated are on the Automated Logic BAS. We are planning on doing them in groups, as evaluated by retro commissioning agents. It will take several years to do all of them.

Justification:

The County has scheduled upgrades in regard to deferred maintenance of Control Systems that must be addressed to improve facility efficiencies. Failure to upgrade the County's existing facilities will result in more expensive deferred maintenance, as well as potential closure of certain areas. Control Systems must operate at a high level of functionality to ensure a comfortable temperature, and air quality, which is critical to building occupancy and functionality. Well-maintained Control systems are also important because they are linked to energy conservation.

HCED continues to experience the effects of previous years’ inflation regarding materials and labor for construction projects.  Although inflation for costs of materials and labor is expected to increase at historical averages in FY2025, the increases from previous years are expected to remain.

 

Alternatives and Engagement:

Not funding this program would lead to an even greater backlog of deferred maintenance to perform later and, in some cases, could create hazards to life and safety.  Delay in project timeline may increase costs due to increased deterioration of infrastructure, potential bid increases, and increase in material and labor costs.

 

Anticipated Project Expenditures and Timeline:

Scope of Work

FY2025 Estimated Cost

Estimated Completion

Upgrades of Control Systems for various buildings countywide  

5900 Canal Control Systems implementation and instillation

$250K

FY2025

Annex 50 (Juvenile Detention) Control Systems implementation and instillation

$500K

FY2025

Family Law Control Systems implementation and installation

$300K

FY2025

Annex 22 Control Systems implementation and installation

$150K

FY2025

Annex 46 Control Systems implementation and installation

$300K

FY2025

Facilities Indicated by the Retro Commissioning Agent

$950K

 

Contingency on Projects

$490K

 

Total FY2025 projects

$2,940K

 

Unencumbered current balance

$(1,300)K

 

Total

$1,640K

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

X Environment

X Governance and Customer Service

 

Previous Court Action:

Date

Agenda Item #

Action Taken

8/29/2023

23.15

Request for approval of a Final Investment Memo for the Control Systems Repair and Replacement Countywide project for a total FY23 & FY24 authorization of $1,567,000.

12/19/2023 

23.23

Request for approval of commercial paper funding for the Office of the County Engineer for the Control Systems Repair and Replacement Countywide project in the amount of $1,570,000.

 

Address:

Precinct(s): Choose an item.

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

Anticipated Court Date: 09/19/2024

Anticipated Implementation Date (if different from Court date):

Legal funding compliance confirmed by: Paige Abernathy, Assistant County Attorney, 7/19/2024

Department Approval by: Rosalie Brockman. Director - Building Resiliency & Sustainability Operations

OMB CIP Team Approval by: Wanwei Tang, Analyst - Capital Projects and Infrastructure, 8/12/24

 

 