Legislation Details

File #: 26-0274    Version: 1 Name:
Type: Report Status: Passed
File created: 12/22/2025 In control: Commissioners Court
On agenda: 1/8/2026 Final action: 1/8/2026
Title: Request for approval of a study report prepared by Civitas Engineering Group Inc., for West Riley Fuzzel Rd- from IH 45 to 200-ft West of West Hardy Rd - 2019, UPIN 20104MF1BY01, Precinct 3.

Primary Department: Purchasing

Primary Department Head/Elected Official: Kimberly J. Williams, JD, Purchasing Agent

 

Secondary Department: County Engineer

Secondary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Report

 

Project ID (if applicable): 20104MF1BY01

Vendor/Entity Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a study report prepared by Civitas Engineering Group Inc., for West Riley Fuzzel Rd- from IH 45 to 200-ft West of West Hardy Rd - 2019, UPIN 20104MF1BY01, Precinct 3.

end

 

Background and Discussion:

This project consists of upgrading West Riley Fuzzel Rd from IH 45 to 200-ft West of West Hardy Rd, from existing 2-lane asphalt roadway to a 4-lane concrete curb and gutter boulevard, with 32' raised median, within a 100' ROW.

 

Expected Impact:

The project will improve the existent conditions of the subject road for the community in the specified area.

 

Alternative Options:

Without this project, this road segment will continue operating under the current conditions without the improved 4 lane configuration.

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): West Riley Fuzzel Rd & Northgate Crossing Blvd, Spring, TX 77373

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

 

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 1/8/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services,

Office of the County Engineer

 

Attachments (if applicable): Study Report