Title: Request for approval of the Final Investment Memo for the Mercer Sanitary Sewer System Connection project for an initial amount of $530,000 and initial commercial paper funding in the amount of $530,000, MWDBE Contracted Goal: 23%, MWDBE Current Achievement: 23% or more.

Department: Commissioner, Precinct 3

Department Head: Commissioner Tom Ramsey

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Mercer Sanitary Sewer System Connection

Project ID (if applicable):  UPIN 23103MF2RQ01

Vendor Legal Name (if applicable):  TBD

 

MWDBE Contracted Goal (if applicable):  23%

MWDBE Current Achievement (if applicable):  23% or more

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Managing Entity: Commissioner Precinct 3    

 

Incremental Authorization Requested: $530,000

Total Estimated Project Cost:  $530,000

 

Request Summary:

title 

Request for approval of the Final Investment Memo for the Mercer Sanitary Sewer System Connection project for an initial amount of $530,000 and initial commercial paper funding in the amount of $530,000, MWDBE Contracted Goal: 23%, MWDBE Current Achievement:  23% or more.  

end

Project Description:

The project will connect both the Mercer Botanical Gardens and the Baldwin Boettcher Library to the public sewer system. 

 

Project Scope:

The project will construct approximately 850’ of sewer line and connect both the Mercer Botanical Gardens and the Baldwin Boettcher Library to the public sewer system.  The project also includes a meter and tap fee to pay for improved connections to public water service for this area of the park.  The water service improvements will also benefit both the library and the botanic gardens.

 

 

Justification:

This project will benefit residents by providing more reliable, healthier source of water.

 

Alternatives and Engagement:

The current septic system at Mercer Botanical Gardens is inadecuate because it is out of code, and because it relies on well water.  The new arrangement will significantly reduce our use of well water, and will bring the systems up to code.  Furthermore, these improvements will reduce ongoing maintenance expence by eliminating one lift station.

 

Anticipated Project Expenditures and Timeline:

Scope of Work

Quantity

Estimated Cost

Estimated Completion

Meter and Tap fee

1

$150,000

Q2 2024

Sewer Line Construction and Connections

850’

$343,600

Q3 2024

Contingency

 

$36,400

 

TOTAL

 

$530,000

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

X Public Health

_ Transportation

_ Flooding

X Environment

X Governance and Customer Service

 

Previous Court Action:

Date

Agenda Item #

Action Taken

10/31/23

385

Transmittal from the Office of the Purchasing Agent was accepted to advertise for construction of a new sanitary sewer system at Mercer Botanical Gardens for Precinct 3.  Job number 230407.

 

 

 

 

 

 

 

Address: Mercer Botanical Gardens, 22306 Aldine Westfield Rd., Humble, TX 77338

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$530,000

$

$

Total Incremental Expenditures

$530,000

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Commercial Paper

$530,000

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$530,000

$

$

Total Funding Sources

$530,000

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: 01/09/24

Anticipated Implementation Date (if different from Court date):  Q1 and Q2, and complete in Q3, 2024

Legal funding compliance confirmed by: Paige Abernathy, Assistant County Attorney, 12/28/2023

Department Approval by: Curt Kates, Director - Budget & Finance

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects and Infrastructure, 12/28/2023

 

 

Commercial Paper Request (For OMB use only):

Receiving Department: Commissioner, Precinct 3

Project PeopleSoft ID: TBD

CP Series Description: Commercial Paper Series D-3 can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the Mercer Sanitary Sewer System Connection project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.OMB Financial Management contact: Amy Perez, Deputy Executive Director, Office of Management and Budget