Legislation Details

File #: 26-5957    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/3/2026 In control: Commissioners Court
On agenda: 9/17/2026 Final action:
Title: Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Houmont Park Subdivision Drainage Improvements - 2018, adding 4 calendar days, with an addition in the amount of $16,063.25, Job No. 25/0194-3, HC Road Fund, UPIN 19101MF14G01, Precinct 1, MWBE Contracted Goal: 32.17%, MWBE Current Participation: 56.54%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 25/0194, UPIN 19101MF14G01

Vendor/Entity Legal Name (if applicable): SER Construction Partners LLC

 

MWBE Contracted Goal (if applicable): 32.17%

MWBE Current Participation (if applicable): 56.54%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Houmont Park Subdivision Drainage Improvements - 2018, adding 4 calendar days, with an addition in the amount of $16,063.25, Job No. 25/0194-3, HC Road Fund, UPIN 19101MF14G01, Precinct 1, MWBE Contracted Goal: 32.17%, MWBE Current Participation: 56.54%.

end

 

Background and Discussion:

The Houmont Park Subdivision Drainage Improvements - HCFCD Unit No. P110-04-00 & P110-00-00 project site consists of subdivision drainage and roadway improvements located between C E King Parkway and Van Hut Lane. The project includes roadside ditch improvements along Unison Rd and Ticonderoga Rd and channel improvements on P110-04-00 and P110-00-00. Two detention basins will be excavated to mitigate for the conveyance improvements for this project.

 

The change in contract includes the following:

 

The line items are adjusted to reconcile overrun quantities and add new line items to the project for completion of the proposed scope of work.

 

         The increase in quantities on overrun line item number 121 for an addition in the amount of $13,740.25 and zero (0) days.

 

Added new line item needed to complete the proposed scope of work.

 

         Added a new line item number 154 for Demolition of the existing septic system in the amount of $2,323.00 and one (1) day.

         Adding three (3) calendar days due to temporary loss of access to Tract 26, which required the Contractor to bypass the affected channel excavation area until Harris County confirmed property acquisition and coordinated access with the property owner, with no additional cost.

 

The above additions result in a net change in the amount of $16,063.25 and four (4) calendar days.

 

The County issued the Project’s Notice to Proceed on 09/22/2025. Per Attachment M of the Contract, the work was to be completed within 600 days of the Notice to Proceed, or by 05/15/2027. With this and all other prior approved change orders, the work is to be completed within 616 days of the Notice to Proceed, or by 05/31/2027.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in Houmont Park subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06/06/2025

282 (25-3822)

Transmittal - Advertisement

08/26/2025

301 (25-5364)

Contract Award - SER Construction Partners LLC

03/19/2026

58 (26-1636)

Contract Amendment (25/0194-1) for additional funds and extension of project term - HC Road Fund

07/09/2026

24 (26-4160)

Contract Amendment (25/0194-2) for additional funds and extension of project term - HC Road Fund

 

Location: Houmont Park Subdivision - P110-04-00 and P110-00-00

Address (if applicable): N/A

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3021

$

$16,063.25

$16,063.25

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$16,063.25

$16,063.25

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$16,063.25

$16,063.25

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 09/17/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC)