Title: Request for approval of an amendment to an agreement with Halff Associates, Inc., in the amount of $100,000, to provide construction phase and additional engineering services for South Mayde Creek Channel Conveyance Improvements (Addicks Reservoir Watershed, Bond ID C-36, Project ID U101-00-00-E002, Agreement No. 2023-51, Precinct 4, MWBE Contracted Goal: 19.11%, MWBE Current Participation: 17.68%).
Attachments: 1. 091726 AMEND HALFF 2023-51 PCT 4 backup.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: Flood Control District

Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): U101-00-00-E002

Vendor/Entity Legal Name (if applicable): Halff Associates, Inc.

 

MWBE Contracted Goal (if applicable): 19.11%

MWBE Current Participation (if applicable): 17.68%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with Halff Associates, Inc., in the amount of $100,000, to provide construction phase and additional engineering services for South Mayde Creek Channel Conveyance Improvements (Addicks Reservoir Watershed, Bond ID C-36, Project ID U101-00-00-E002, Agreement No. 2023-51, Precinct 4, MWBE Contracted Goal: 19.11%, MWBE Current Participation: 17.68%).

end

 

Background and Discussion:

This amendment will provide final design services for a No-Rise Analysis based on FEMA effective models, as-built (post-construction) survey, encroachment exhibits, combined bidding for this project and the attached U501-06-00-E002 stormwater detention basin, and additional geotechnical investigations for the existing aerial waterline to be relocated under the channel for South Mayde Creek Channel Conveyance Improvements. This project includes channel conveyance improvements along Lower South Mayde Creek (U101-00-00) from Greenhouse Road to Fry Road.  Final design was funded by the 2018 Bond Program and approved by Commissioner’s Court on June 4, 2024.  Due to permitting requirements, scope changes to the CDBG process, changes to the environmental process, and additional items required during design, additional funds are required to complete the project.  Additional funds are required for the following items: No-Rise analysis based on FEMA effective models, as-built (post-construction) survey, encroachment surveys, combined bidding for this project and the attached U501-06-00-E002 stormwater detention basin, and additional geotechnical investigations for the existing aerial waterline to be relocated under the channel.  To continue moving the project forward, funds were re-allocated from the revisions, bidding, and construction phases and are planned to be replenished with this RCA. This amendment is needed to provide design services for a No-Rise Analysis based on FEMA effective models, as-built (post-construction) survey, encroachment exhibits, combined bidding for this project and the attached U501-06-00-E002 stormwater detention basin, and additional geotechnical investigations for the existing aerial waterline to be relocated under the channel.

 

Expected Impact:

The project seeks to reduce flood risks and strengthen resiliency in the Addicks Reservoir watershed by reducing Water Surface Elevation up to 0.68 feet during the 100-yr storm event and includes the removal of 158 structures, 3.5 miles of roadway and 83.1 acres from the floodplain area. 

 

Alternative Options:

The alternative to approving this item would be to select another firm for this assignment, which would result in delays in completing this project. Based on grant requirements, support of design transition to a new team would be on the critical path, which is dependent on a project completion in 2028. 

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H1: Complete and implement the Flood Resilience Plan.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

07/11/2017

2.d.1.

ATN

03/27/2018

2.a.4.

Agreement

01/28/2020

2.a.5.

Amendment to Agreement

02/09/2021

89.

PER Acceptance

06/04/2024

196.

Agreement

 

Location: N/A

Address (if applicable):

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

4.a.3 - Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$100,000

$100,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$100,000

$100,000

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$100,000

$100,000

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 9/17/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Agreement