File #: 25-0943    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/25/2025 In control: Commissioners Court
On agenda: 2/6/2025 Final action: 2/6/2025
Title: Request for approval of a change in contract with MC2 Civil, LLC, in connection with final construction of Intersection Improvement - Katy Hockley Road at Clay Road - 2022, adding 259 calendar days, with no change in the amount, Job No. 22/0230-3, UPIN 23104MF2PP01, Precinct 4, MWBE Contracted Goal: 32%, MWBE Current Participation: 35.45%.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: Commissioner, Precinct 4

Secondary Department Head/Elected Official: Lesley Briones

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0230, UPIN 23104MF2PP01 

Vendor/Entity Legal Name (if applicable): MC2 Civil, LLC

 

MWBE Contracted Goal (if applicable): 32%

MWBE Current Participation (if applicable): 35.45%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with MC2 Civil, LLC, in connection with final construction of Intersection Improvement - Katy Hockley Road at Clay Road - 2022, adding 259 calendar days, with no change in the amount, Job No. 22/0230-3, UPIN 23104MF2PP01, Precinct 4, MWBE Contracted Goal: 32%, MWBE Current Participation: 35.45%.

end

 

Background and Discussion:

This project is for the asphalt paving improvements and roadway widening at Clay and Katy Hockley - Harris County Precinct 4.

 

The change involves a 259-calendar-day extension in contract time.  The additional time is necessary to complete the project due to prolonged delays caused by conflicts with existing Kinder Morgan pipelines.

 

Added Items:

•                     PCO #4 - Time extension, adding 259 calendar days to the contract.

 

The project was completed to improve and provide reliable and safe route of transportation to residents of Harris County.

 

 

Expected Impact:

The proposed final change order allows an extension of the contract duration, compensation for the contractor's work, and the return of unused funds to the precinct.

 

Alternative Options:

There are no alternative options or contractor will be delayed for payment of his final pay estimates which include the retainage.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/13/2022

22-5352

Contract Award

04/23/2024

24-2111

Contract Amendment #1 for additional funds and extension of project term

05/07/2024

24-2708

Contract Amendment #2 for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 2/6/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Engineering Department

 

Attachments (if applicable): County Auditor’s Form 1258B