Title: Request for approval to reject the proposal(s) received for construction of floating vegetated islands at Rev. William and Audrey Lawson Stormwater Detention Basin for the Flood Control District, and that the project be readvertised at a later date with revised specifications (240356).
Attachments: 1. 25-0780 Rejection Job No. 240356

Primary Department: Purchasing

Primary Department Head/Elected Official: Paige McInnis

 

Secondary Department: Flood Control District

Secondary Department Head/Elected Official: Tina Petersen

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Proposals/Bids

 

Project ID (if applicable): 240356

Vendor/Entity Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

 

Request Summary (Agenda Caption):.

title

Request for approval to reject the proposal(s) received for construction of floating vegetated islands at Rev. William and Audrey Lawson Stormwater Detention Basin for the Flood Control District, and that the project be readvertised at a later date with revised specifications (240356).

end

 

Background and Discussion:

The project area is in Southeastern Harris County within Precinct 1 inside the of Unincorporated Houston at Clear Creek Watershed. The goal of the Floating Vegetated Islands is to provide the environmental stormwater quality benefits to the existing Stormwater Detention Basin Project (A500-08-00-E002). The design was completed by B2Z Engineering team. The construction of the proposed vegetated island is funded by the 2018 Bond (C-05).

 

 

Expected Impact:

The objective of this project is to enhance stormwater quality to the Clear Creek Channel, HCFCD Unit A100-00-00.

 

 

Alternative Options:

There is no alternative option for this project.

 

 

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H1: Complete and implement the Flood Resilience Plan.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): Project is bounded by Cullen Blvd. to the West and Clear Creek (Unit A100-00-00) to the to the East .

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 2/6/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Rashaun Jones, Project Manager, Capital Projects North; Kenneth Jackson, Sourcing Manager, Purchasing

 

Attachments (if applicable): Letter