Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): 23103MF2TY01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy, LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills for 17250 ½ Telge Rd, Cypress, Texas 77002 (intersection of Telge Road at Grant Road) for electrical power serving a traffic signal, Precinct 3.
end
Background and Discussion:
Traffic Signal - Telge Road at Grant Road is a project to install a temporary signal to enhance traffic movement. The service outlet location statement is needed to establish electrical service from CenterPoint Energy to power the temporary traffic signal.
Expected Impact:
Approval of the service outlet location statement will allow CenterPoint Energy to establish electrical service to the temporary traffic signal, which is needed to enhance the operation of the intersection of Telge Road at Grant Road.
Alternative Options:
All traffic signals require a power source, which is typically obtained through CenterPoint Energy. Alternative options are to place a generator, which is not reliable, or not installed the signal from the intersection. Both options will impact the operation and increase delay at the intersection.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any): List all instances of prior Commissioners Court action that relates to this item (Original Project Award).
Date |
Agenda Item # |
Action Taken |
|
|
|
Location:
Address (if applicable): 17250 ½ Telge Rd, Cypress, Texas 77002
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
Road and Bridge Program |
|
FY 24 |
FY 25 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$900 |
$1200 |
$3600 |
Total Incremental Expenditures |
$900 |
$1200 |
$3600 |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
1000 - General Fund |
$900 |
$1200 |
$3600 |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$900 |
$1200 |
$3600 |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$900 |
$1200 |
$3600 |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: November 14th, 2023
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Patrick Mandapaka, PhD., AICP, Director of Community Resilience &
Transportation Planning, HCED
Attachments (if applicable): SOLS