File #: 25-6866    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 10/17/2025 In control: Commissioners Court
On agenda: 10/30/2025 Final action: 10/30/2025
Title: Request for approval of an award on the basis of low bid to Statewide Traffic Signal Company in the amount of $1,466,734 for installation and modification of traffic signals and related improvements along Memorial Drive for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (250224), MWBE Contracted Goal: 16.91%.

Primary Department: Purchasing

Primary Department Head/Elected Official: Kimberly J. Williams, JD

 

Secondary Department: Commissioner, Precinct 3

Secondary Department Head/Elected Official: Tom Ramsey

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 250224

Vendor/Entity Legal Name (if applicable): Statewide Traffic Signal Company

 

MWBE Contracted Goal (if applicable): 16.91%

MWBE Current Participation (if applicable):

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

 

Request Summary (Agenda Caption):

title

Request for approval of an award on the basis of low bid to Statewide Traffic Signal Company in the amount of $1,466,734 for installation and modification of traffic signals and related improvements along Memorial Drive for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (250224), MWBE Contracted Goal: 16.91%.

end

 

Background and Discussion:

Request for approval to award contract to Statewide Traffic Signal Company for rebuilding three traffic signals in the City of Piney Point Village, UPIN: 23103MF2V801, Precinct 3, MWDBE Contracted Goal: 16.91%.

 

Traffic signals are rebuilt to improve the operation of an intersection and better facilitate pedestrian activities. The existing traffic signals in the City of Piney Point Village were installed over 20 years ago. Re-building these signals will ensure the intersections are brough up to compliance with current standards and provide pedestrian connectivity. This rebuild project is a collaborative effort between City of Piney Point Village, Precinct 3, and the Office of the County Engineer (OCE).

 

Expected Impact:

Rebuilding the traffic signals will bring the infrastructure to current standards and specifications and reduce overall maintenance cost. It will also significantly reduce the risk of failure during a catastrophic event.

 

Alternative Options:

Should the award recommendation not be executed, rebidding the project will be required, which will extend the existing project schedule.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/31/2023

97

Request for approval to negotiate with Traf-IQ, Inc. to provide Professional Engineering Services.

10/31/2023

39

Request for approval to execute an agreement with Traf-IQ, Inc. to provide Professional Engineering Services.

01/30/2024

299

Request for approval to execute an Interlocal Agreement with the City of Piney Point Village

08/07/2025

457

Advertisement Letter

 

Location:

Address (if applicable): City of Piney Point Village: Memorial Drive - Blalock Road, Piney Point Road, and

San Felipe Drive

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Installation and Modification of Traffic Signals and Related Improvements along Memorial Drive for Harris County Precinct 3

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other

$

$1,466,734.14

$1,466,734.14

$

Other  3109-10306201-811009

$

$473,854.20

$473,854.20

$

Other  3109-10392100-811009

$

$992,879.94

$992,879.94

$

Total Existing Budget

$0

$1,466,734.14

$1,466,734.14

$0

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$0

$1,466,734.14

$1,466,734.14

$0

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 10/30/2025

Anticipated Implementation Date (if different from Court date): 10/30/2025

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief, Engineering & Architectural Services, OCE; Lyndsey Bars, Senior Buyer, Purchasing

 

Attachments (if applicable): Letter, Bid Tab