Legislation Details

File #: 26-0930    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/29/2026 In control: Commissioners Court
On agenda: 2/12/2026 Final action: 2/12/2026
Title: Request for approval of a change in contract with CE Barker, LTD, in connection with Sanitary Sewer System Construction - Westfield Estates - 2023, adding 102 calendar days, with an addition in the amount of $35,301.89, Job No. 24/0313-1, UPIN 23208MF2XZ01, Precinct 2, MWBE Contracted Goal: 19.82%, MWBE Current Participation: 8.06%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0313, UPIN 23208MF2XZ01

Vendor/Entity Legal Name (if applicable): CE Barker, LTD

 

MWBE Contracted Goal (if applicable): 19.82%

MWBE Current Participation (if applicable): 8.06%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

                     

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with CE Barker, LTD, in connection with Sanitary Sewer System Construction - Westfield Estates - 2023, adding 102 calendar days, with an addition in the amount of $35,301.89, Job No. 24/0313-1, UPIN 23208MF2XZ01, Precinct 2, MWBE Contracted Goal: 19.82%, MWBE Current Participation: 8.06%.

end

 

Background and Discussion:

Harris County Office of the County Engineer received American Rescue Plan Act (ARPA) funding for wastewater and water projects.  Through a vetting process, the Westfield Estates Sanitary Sewer System project was selected.  The project scope includes sanitary sewer lines, manholes, a lift station and a force main, as well as connecting properties to the new system and abandoning existing septic systems.  This initiative addresses environmental concerns by replacing failing septic systems that risk contaminating roadside ditches and nearby waterways.

 

This change order is tied to PCO -1 and 2. PCO-1: The delay in acquiring the property for the sanitary lift station located at 2302 Chamberlain Street prevented the contractor from starting critical work as scheduled on January 27, 2025, impacting on the project’s critical path.  Harris County’s late completion of the property acquisition on May 20, 2025, delayed the construction of the lift station, as well as the procurement of piping materials, electrical equipment, and the backup generator.  A Time Impact Analysis confirmed that this delay shifted the project’s substantial completion date from July 20, 2026, to October 30, 2026, an extension of 102 calendar days. Consequently, both the Office of the County Engineer (OCE) and the Engineer of Record (EOR) recommend approving a 102-day time extension through a Change Order.

PCO-2: The Change Order incorporates the installation of the third base elbow, along with the necessary coatings, guide rails, and riser pipe, into the top slab during the current construction phase to accommodate a potential future third pump.  Completing this work now avoids extensive future underground tasks such as bypassing the lift station, coring the slab, and repouring concrete which would be more costly and disruptive. Including these items at this stage ensures proper alignment, minimizes future downtime, and enhances long-term operational efficiency.  The proposed Change Order adds an additional cost of $35,301.89

The Combined total for PCO-1 and PCO-2 is $35,301.89, representing approximately 0.17% of the total project budget, with an additional time of 102 calendar days.

 

The County issued the Project’s Notice to Proceed on January 27, 2025.  Per Section 5.3 of the Contract’s General Conditions, the work was to be completed within 540 days of the Notice to Proceed, or by July 20, 2026.   With this and all other prior approved change orders, the work is to be completed within 642 days of the Notice to Proceed, or by October 30, 2026.

 

Expected Impact:

The changes add additional cost to the contract, ensuring the project aligns with its originally intended objectives. This change order adds $35,301.89 to the project contract amount and extends the contract duration by 102 calendar days, adjusting the project completion date to October 30, 2026.

Alternative Options:

No alternative options: If no action is taken, the sanitary system and other infrastructure constructions will not be completed.  

 

Funding source: 2651 - American Rescue Plan 2021

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

10/29/2024

20 (24-6859)

Contract Award

 

Location:

Address (if applicable): Westfield Estates Subdivision

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

2651 - American Rescue Plan 2021

$

$35,301.89

$35,301.89

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$35,301.89

$35,301.89

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$35,301.89

$35,301.89

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 2/12/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B