Title: Request for approval of an award on the basis of best proposal meeting requirements to CFI Mechanical, Inc. in the amount of $5,360,268 for 1010 Lamar (Annex 48) stairwell pressurization, Heating, Ventilation, and Air Conditioning (HVAC) repair & plumbing renovations for the Office of the County Engineer and for the County Clerk to execute any applicable bonds to be received (260063), MWBE Contracted Goal: 10.4%.

Primary Department: Purchasing

Primary Department Head/Elected Official: Kimberly J. Williams, JD

 

Secondary Department: County Engineer

Secondary Department Head/Elected Official: Milton Rahman

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 260063

Vendor/Entity Legal Name (if applicable): CFI Mechanical, Inc.

 

MWBE Contracted Goal (if applicable): 10.4%

MWBE Current Participation (if applicable):

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an award on the basis of best proposal meeting requirements to CFI Mechanical, Inc. in the amount of $5,360,268 for 1010 Lamar (Annex 48) stairwell pressurization, Heating, Ventilation, and Air Conditioning (HVAC) repair & plumbing renovations for the Office of the County Engineer and for the County Clerk to execute any applicable bonds to be received (260063), MWBE Contracted Goal: 10.4%.

end

 

Background and Discussion:

The project scope is split into two distinct scope packages:

 

Stair Pressurization Project: This package includes the Engineering and design to provide a code compliant Stair Pressurization system to the existing building. Two fans will be located on the roof, one for each stair. This includes new vertical risers in fire rated shafts from the roof down to the first floor. This project also includes a new 277/480v-3ph4W. 60KW/75KVA natural gas generator to provide emergency back-up power to the new Stair Pressurization Fans.

 

Chilled Water Upgrades: This project includes connecting the building to Centrio Energy's underground chilled water distribution system. The scope is to connect to Centrio's provided heat exchangers down in the basement level of the 1111 Main St. garage, install new chilled water pumps on the first floor of the garage that will provide chilled water to the buildings Air Handling Units via new chilled water piping. Once connected to Centrio's chilled water system the existing water-cooled Chillers, chilled water pumps, condenser water pumps, Cooling Tower and all associated supports are to be removed from the building and disposed of. All aforementioned equipment is located on the roof and the 19th floor of 1010 Lamar.

 

 

Expected Impact:

The project objectives are to modernize the building’s critical stairwell pressurization system for fire safety and increase the operational capacity of Annex 48’s HVAC system to meet the current demand.

 

Alternative Options:

No other recommended option for this identified need.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

1/29/26

196

Approved - Request for approval of a project scheduled for advertisement on behalf of Pollution Control Services; 101 S. Richey St (John Phelps Courthouse)

3/26/24

127

Request for approval of a Final Investment Memo for the 1010 Lamr - Renovations project for an additional $20,000,000 for a total of $29,500,000 and for approval of additional commercial paper funding in the amount of $12,000,000 for a total of $21,500,000

11/12/24

111

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an incremental authorization of $9,464,000 for a total FY2025 authorization of $9,864,000 amd request for commercial paper funding for an amount of $1,000,000

12/10/24

119

Request for approval of a Final Investment Memo for the Heating, Cooling, Ventilation Air Conditioning (HVAC) Replacement Countywide project for an incremental authorization of $35,115,000 for an FY2025 total authorization of $35,940,000

1/23/25

30

Request for approval of the Final Investment Memo for the Plumbing Systems Repair and Replacement project for an additional incremental authorization of $13,895,000 for a total FY2025 authorization of $15,295,000

3/19/26

194

Request for approval of a project scheduled for advertisement for 1010 Lamar (Annex 48) stairwell pressurization, heating, ventilation, and air conditioning (HVAC) repair & plumbing renovations for the Office of the County Engineer

 

Location:

Address (if applicable): 1010 Lamar St., Houston, TX 77002

Precinct(s): Countywide

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$5,360,268

$5,360,268

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$5,360,268

$5,360,268

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$5,360,268

$5,360,268

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 5/28/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department:

Jesus A. Venegas, Project Manager, Office of the County Engineer - Vertical Construction & Design

Michael Burtner, Project Manager, Office of the County Engineer - Vertical Construction & Design

Andreas Peeples, Director, Office of the County Engineer - Vertical Construction & Design

Margaret Obot, Sr. Sourcing Manager, Purchasing

 

Attachments (if applicable): Letter, Proposal