File #: 24-6091    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/23/2024 In control: Commissioners Court
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Request for approval of a change in contract with Frost Construction Co Inc., in connection with Deussen Park Maintenance Barn Renovation - 2022, adding 2 calendar days, with an addition in the amount of $26,717.55, Job No. 23/0435-2, UPIN 22101MF26401, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 18.70%.

Department: County Engineer

Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 23/0435

Vendor/Entity Legal Name (if applicable): Frost Construction Co. Inc

 

MWDBE Contracted Goal (if applicable): 20%

MWDBE Current Participation (if applicable): 18.70%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Frost Construction Co Inc., in connection with Deussen Park Maintenance Barn Renovation - 2022, adding 2 calendar days, with an addition in the amount of $26,717.55, Job No. 23/0435-2, UPIN 22101MF26401, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 18.70%.

end

 

Background and Discussion:

Existing parks maintenance facility consisting of two (2) steel buildings on concrete pads erected in about 1970’s. One of the buildings has severe deterioration to the structural framing occurring at the base of the rigid steel frame. Existing office staff amenities of breakroom and restrooms are outdated and in poor condition. Asbestos has been identified in the facility and needs to be addressed. The site condition has ponding issues with stagnate water after rainfall.

 

Changes included here involve: Additional electrical gutters to better accommodate both existing and new electrical lines, owner request to procure furniture not originally captured in base bid, owner request to remove & replace two (2) fan power boxes not originally captured in base bid, owner request to perform repair work on building metal exterior not originally part of scope.

 

Expected Impact:

These changes allow the contractor to bill for required changes resulting from unforeseen conditions and Owner Requests.

 

Alternative Options:

Should we not move forward with this change in contract, these items will remain unreconciled delaying the closeout of the contract and project.

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/14/23

283

Advertisement of Project Approved

12/19/23

276

Contract - Award

06/04/24

73

Request for approval of a change in contract with Frost Construction Company, Inc. in connection with Maintenance Barn at Deussen Park - Renovation - 2022, adding 16 calendar days, with an addition in the amount of $79,598.36, Job No. 23/0435, UPIN 22101MF26401, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 20%

 

Location:

Address (if applicable): 12303 Sonnier St. #Bldg M, Houston, TX 77044

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$26,717.55

$26,717.55

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$26,717.55

$26,717.55

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$26,717.55

$26,717.55

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: October 8th,2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department:

Truitt Rounsavall, PE, MBA, PMP, LSSBB; Interim Director - HCED Vertical Construction - Engineering Group

Jesus A. Venegas; PM - Construction, HCED Vertical Construction - Engineering Group

 

Attachments (if applicable): County Auditor’s Form 1258B (Job No. 23/0435-2)