Legislation Details

File #: 24-4729    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 7/25/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval of a change in contract with MB Western Industrial Contracting Co. in connection with final construction of Hike and Bike Trail - Willow Waterhole Detention Basin - 2020, adding 93 calendar days, with an addition in the amount of $10,544.77, Job No. 22/0413-2, UPIN 20101MF1JD01, Precinct 1, MWDBE Contracted Goal: 30%, MWDBE Current Participation: 100%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer

 

 

Regular or Supplemental RCA: Regular RCAType of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0413, UPIN 20101MF1JD01

Vendor/Entity Legal Name (if applicable): MB Western Industrial Contracting Co.

 

MWDBE Contracted Goal (if applicable): 30%

MWDBE Current Participation (if applicable): 100%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with MB Western Industrial Contracting Co. in connection with final construction of Hike and Bike Trail - Willow Waterhole Detention Basin - 2020, adding 93 calendar days, with an addition in the amount of $10,544.77, Job No. 22/0413-2, UPIN 20101MF1JD01, Precinct 1, MWDBE Contracted Goal: 30%, MWDBE Current Participation: 100%.

end

 

Background and Discussion:

The project is to provide 2.94 miles concrete trail and 0.6-mile earth trail within Willow Waterhole Detention

Basin.

 

This change in contract includes:

 

(PCO-3) The addition of 15 days due to the time needed to change the design of proposed bollards along the trail.

 

(PCO-4) The addition of RCP, SET’s and concrete collars for driveway called out in the plans and 10 days. Increase quantity for item #20 Concrete Collar by 2 each, item #21 Reinforced Concrete Pipe by 24 LF and Item #22 SET (Type II) (24”) (RCP). Total Amount =$18,320.00.

 

(PCO-5) The addition of 5 days to remove existing corrugated pipe in conflict with proposed trail.

 

(PCO-6) The addition of 12 days for the time needed to review and revise the trail elevations.

 

(PCO-7) The addition of 36 days for the time to excavate excess quantity from bid item-excavation.

 

(PCO-8) The addition of 5 days due to work stoppage to accommodate Willow Waterhole parks organization event.

 

(PCO-9) The addition of line item #38 to remove and replace concrete at an existing bench = $6,600.60. 

The addition of line item #39 to remove and replace concrete around existing water fountain = $4,815.91

The addition of new line item to construct a concrete curb wall near existing backslope interceptors and an additional 10 days = $16,533.87.

The addition of line item #42 to construct 100 liner feet of drainage swale near new trail = 4,281.75

Total Amount = $32,232.13

 

(PCO-10) The Final Adjustment is a deduction of -$40,007.36 and 0 days.

 

Expected Impact:

Changes allow for compensation to the Contractor for actual quantities used in construction, in accordance with the original intent of the project.

 

Alternative Options:

Revise original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_X Transportation

_X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/31/2023

23-0420

Contract Award

10/10/2023

23-6004

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable): 1000 S. Post Oak Houston, TX 77002

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$10,544.77

$10,544.77

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$10,544.77

$10,544.77

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$10,544.77

$10,544.77

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: August 06, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B