File #: 25-6175    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/30/2025 In control: Commissioners Court
On agenda: 10/16/2025 Final action: 10/16/2025
Title: Request for approval of an amendment to an agreement with PGAL, Inc., for Construction Phase Services in the amount of $ 16,883.00 for the Recovery and Resiliency Division (RRD) Barrett Station (Phase 2 - Barrett Settlement & St. Charles Place) Subdivision Drainage Improvements - 2018, UPIN 19102MF14Q01, Precinct 3, MWBE Contracted Goal: 31%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN 19102MF14Q01

Vendor/Entity Legal Name (if applicable): PGAL, Inc.

 

MWBE Contracted Goal (if applicable): 31%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with PGAL, Inc., for Construction Phase Services in the amount of $ 16,883.00 for the Recovery and Resiliency Division (RRD) Barrett Station (Phase 2 - Barrett Settlement & St. Charles Place) Subdivision Drainage Improvements - 2018, UPIN 19102MF14Q01, Precinct 3, MWBE Contracted Goal: 31%.

end

 

Background and Discussion:

Barrett Station (Phase 2 - Barrett Settlement & St. Charles Place) Subdivision Drainage Improvements is located in northeast Harris County in the San Jacinto watershed with a small portion in the Cedar Bayou watershed. It is to the south of Barrett Road, east of Crosby-Lynchburg Road, and north of Cottontail Drive. The existing drainage system is roadside ditches. The proposed improvements are to regrade roadside ditches, upsize culverts to increase capacity, and to construct a detention pond for mitigation.

 

The additional funds will cover the construction phase services agreement to allow for construction oversight of the project.

 

Expected Impact:

This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. Engineering support during the construction of the improvements is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the Barrett Station (Phase 2 - Barrett Settlement & St. Charles Place) Subdivision Project area, Harris County, and FEMA. The fiscal impact for this project will come from the 1080 Fund for the Recovery and Resiliency Division subdivision projects with the long-term goal of reducing drainage costs in the future. No impact to project schedule or staffing anticipated.

 

Alternative Options:

The County could elect to approve the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/26/2022

26 (22-2492)

Contract - Award

09/27/2022

53 (22-5894)

Contract - Amendment

01/30/2024

71 (24-0567)

Contract - Amendment

 

Location: Barrett Station (Phase 2 Barrett Settlement & St. Charles Place)

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

$16,883.00

$16,883.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$16,883.00

$16,883.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$16,883.00

$16,883.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 10/16/2025

Anticipated Implementation Date (if different from Court date): 10/17/2025

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer

 

Attachments (if applicable): Amended Construction Phase Services Agreement