File #: 26-3313    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/14/2026 In control: Commissioners Court
On agenda: 5/28/2026 Final action: 5/28/2026
Title: Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place Phase II Subdivision Drainage Improvements - 2018, adding 306 calendar days, with a deduction in the amount of $525.95, Job No. 23/0178-5, UPIN 23208MF2TN01, Precinct 2, MWBE Contracted Goal: 24%, MWBE Current Participation: 100%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0178, UPIN 23208MF2TN01

Vendor/Entity Legal Name (if applicable): Reliance Construction Services, L.P.

 

MWBE Contracted Goal (if applicable): 24%

MWBE Current Participation (if applicable): 100%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place Phase II Subdivision Drainage Improvements - 2018, adding 306 calendar days, with a deduction in the amount of $525.95, Job No. 23/0178-5, UPIN 23208MF2TN01, Precinct 2, MWBE Contracted Goal: 24%, MWBE Current Participation: 100%.

end

 

Background and Discussion:

The Beaumont Place Subdivision is located in the Greens Bayou watershed near Highway 90 and Beltway 8. The proposed improvements include roadside ditch regrading, driveway culvert upgrades, expansion of channel along Big Gulch, concrete lined Sulphur Gully channel with reinforced concrete box (RCB) crossing improvements. Improvements also include multiple detention ponds along Big Gulch with an extreme event overflow swale towards the upstream portion of the channel.

 

The change in contract includes the following:

 

The line items are adjusted to reconcile overrun, underrun quantities and add new line items to the project for completion of the proposed scope of work.

 

         The increase in quantities for existing line items 5, 6, 7, 9, 17, 19, 24, 36, 37, 38, 40, 49, 130, 135, 148, 157, 183, 184, 185, and 192 for an addition in the amount of $503,122.41.  

 

         The decrease in quantities for existing line items 27, 42, 60, 84, 129, 146, 160, 162, and 198 for a deduction in the amount of -$1,047,305.28.

 

New Items:

 

         Added new line item 220 for furnishing and installing 48-inch Corrugated Metal Pipe for an addition in the amount of $31,173.05 and added 3 Days.

         Added new line item 221 for furnishing and installing 24-inch HDPE Pipe - Pond 2 for an addition in the amount of $9,918.22 and added 1 day.

         Added new line item 222 for Furnish and Install Timber Bent for 48-inch CMP Outfall for an addition in the amount of $4,138.85 and added 1 day.

         Added new line item 223 for installation of a cast-in-place 4' x 4' SET (Type 2, 3:1) at Pond 1 and Pond 2 for an addition in the amount of $13,031.12 and 6 days.

         Added new line item 224 for installation of two flow restrictors on Hartman for an addition in the amount of $176,903.72 and 30 days.

         Added new line item 225 for modification of flow restrictors on Hartman at station# 38+00 for an addition in the amount of $25,291.08 and 7 days.

         Added new line item 226 for installation of 121 weep holes along the Hartman Channel bottom for an addition in the amount of $190,501.19 and 30 days.

         Added new line item 229 and 230 for relocation of 8-inch waterline (Royal wood MUD) which was in conflict to install the Riprap at Big gulch outfall for an addition in the amount of $73,597.79 and 60 days.

         Added an addition of 155 days for Design and coordination of the Engineer of Record with Royal wood MUD, Exxon Mobil and HCFCD for Flow restrictors, Waterline relocation, removal and installation of the Storm sewer, manhole and outfall at Kinsman and Rimwood and weep holes.

         Added new line item 231 for providing survey information of the ditches, storm sewer and outfall installed by Phase I contractor at Kinsman and Rimwood for an addition in the amount of $2,049.30 and 5 days.

         Added a new line item 232 for installation of welded caps on abandoned pipelines (7Green and Yoakum) to facilitate ditch restoration on Gladden and Verdun in the amount of $14,052.60 and 2 days.

         Added a new line item 233 for 4-inch wet connection and line item 234 for 4-inch cut & plug in lieu of 6-inch items in the amount of $3,000.00 and 6 days.

 

The above additions and deductions result in a deduction in the amount of ($525.95) and 306 calendar days.

 

The County issued the Project’s Notice to Proceed on 09/11/2023. Per Attachment M of the Contract, the work was to be completed within 640 days of the Notice to Proceed, or by 06/11/2025. With this and all other prior approved change orders, the work is to be completed within 969 days of the Notice to Proceed, or by 05/07/2026.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Beaumont Place subdivision

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

05/16/2023

358 (23-2817)

Transmittal - Advertisement

06/27/2023

258 (23-3607)

Contract Award - Reliance Construction Services, L.P.

12/10/2024

100 (24-7495)

Contract Amendment (23/0178-1) for additional funds

01/23/2025

67 (25-0628)

Contract Amendment (23/0178-2) for additional funds

05/08/2025

137 (25-2651)

Contract Amendment (23/0178-3) for additional funds and extension of project term

07/10/2025

16 (25-4100)

Contract Amendment (23/0178-4) for extension of project term

 

Location: Beaumont Place         Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

-$525.95

-$525.95

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$525.95

-$525.95

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$525.95

-$525.95

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 5/28/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC)