Type: Investment Memo Status: Passed
File created: 8/13/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Request for approval of the Final Investment Memo for Data Center Repair and Replace project for an incremental authorization for $744,346 for a total authorization of $1,819,346 for FY2026.

Primary Department: Universal Services

Primary Department Head/Elected Official: Executive Director and CIO, Sindhu Menon

Managing Department: Universal Services

Managing Department Head/Elected Official: Executive Director and CIO, Sindhu Menon

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name:  Data Center Repair and Replace

Project ID (if applicable): NI039

Vendor Legal Name (if applicable):

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $744,346

Total Estimated Project Cost: $1,819,346 (FY26)

 

Request Summary:

title

Request for approval of the Final Investment Memo for Data Center Repair and Replace project for an incremental authorization for $744,346 for a total authorization of $1,819,346 for FY2026.  

end

 

Project Description:

The Data Center Repair and Replace project is an ongoing project to optimize and enhance all aspects of the data center ecosystem to support the growing technology needs of Universal Services (US). This includes the physical critical infrastructure that supports the delivery of the application to all Harris County users, partners, and patrons. The Data Center Repair and Replace project encompasses improvements to power usage and delivery, thermal management of the data center, the physical security of the data center and hardware enclosers and any software management tools used to analyze hardware performance during the operation of the Enterprise Data Center located in Annex 18.

 

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

Annex 18 (406 Caroline) UPS project finalization

$225,000

1/2026

Purchase Enterprise UPS systems with Nickle Zinc batteries for CJC

$405,000

              07/2026

APC for the 406 DC maintenance in-row power distribution unit maintenance

$50,000

               09/2026

Design work

$100,000

7/30/2025

Construction

$1,039,346

9/30/2026

FY26 Total Authorization

$1,819,346

 

 Unencumbered existing project balance to carry into FY26

($1,075,000)

 

Total

$744,346

 

 

Justification & Alternatives:

Relocating critical electrical systems from the basement follows recommended best practices and will increase efficiencies of the power systems. Replacing and expanding the UPS at the Criminal Justic Center (CJC) or Criminal Courthouse will increase efficiencies and enhance the resiliency of the critical power systems supporting network infrastructure and critical radio hardware. The existing UPS system is over 25 years old and parts are no longer available.

 

Alternatives

Aside from utilizing the more efficient electrical infrastructure, utilizing the nickel-zinc battery technology will allow us to move away from the more volatile lead acid and lithium-ion battery technologies. This will more closely align US with Harris county’s overall climate action and energy conservation goals.  

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): R3: Strengthen the County’s emergency response function.

Housing Initiative (Goal 6): N/A


Decision Analysis Matrix Score (rubric on last page): 19

Previous Court Action:

Date

Agenda Item #

Action Taken

3/22/2022

22-2028

Request for approval of PIM and Commercial Paper funding for $280,000

8/23/2022

22-4953

Request for additional incremental authorization of $495,000, FY 23 total authorization of $775,000

7/18/2023

23-3948

Request for additional incremental authorization of $775,000 for FY24

10/10/2023

23-5833

Request for approval of commercial paper funding $390,000 for a total of $670,000

8/27/2024

24-5144

Request for additional incremental authorization $775,000 FY25

 

Address: Multiple

Precinct(s): Precinct 1

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

 

 

 

$

Other

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

 

$

$

-

 

Anticipated Court Date: 8/26/2025

Anticipated Implementation Date (if different from Court date): 10/1/2025

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, Special Assistant County Attorney, 7/22/2025

Department Approval by: Heather Merkel, Director of Budget, Universal Services 8/8/2025

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 8/7/2025

________________________________________

Commercial Paper Request (For OMB use only):

Receiving Department: N/A

Project PeopleSoft ID: N/A

CP Series Description: N/A

OMB Financial Management contact: N/A

 

 

Decision Analysis Matrix scoring tool - Commissioners Court has approved the rubric below for scoring capital projects. Please complete the last two rows for OMB review.

Scoring option

Strategic Plan alignment (3x weighting)

Evidence base

Impact on outcomes

Cost effectiveness

Ease of implementation

Collaboration / partnerships

Environmental sustainability

Equity

Total

-1

Antithetical to one or more aspects of the Strategic Plan

Evidence shows net negative impact on the intended goal

Impact is clearly negative

Costs expected (or shown) to outweigh benefits

County has no/limited existing capabilities and dependencies are likely to impede

Could negatively impact relationships with partners

Negatively impacts environment and/or climate change mitigation efforts

Inequitable

n/a

0

Does not align to a Strategic Objective

Evidence base is not well defined or measurable

Size of impact on one or more strategic outcomes is negligible or unclear

Net comparison is unclear

County has no/limited existing capabilities or dependencies are likely to impede

Does not involve collaboration with partners

Net neutral impact on environment and/or climate change mitigation efforts

Does not consider equity to a meaningful degree

n/a

1

Aligns to a Strategic Objective but not to a Strategic Initiative

Limited evidence-based research on outcomes; may have qualitative/theoretical support

Outcomes are defined but without target levels and/or expected impact is moderate

Moderate direct/indirect benefit relative to costs

County has existing capability to implement or dependencies are unlikely to impede

Moderately expands County leverage through collaboration with partner(s)

Marginally positive impact on environment and/or climate change mitigation efforts

Considers equity to a meaningful degree, but not comprehensively

n/a

2

Aligns to a Strategic Objective and a Strategic Initiative

Outcomes are directly supported by evidence base or credible research supports anticipated outcomes

Outcomes are clearly defined and include target levels; expected impact on outcomes is high

Significant direct/indirect benefit relative to costs

County has existing capability to implement and dependencies are unlikely to impede

Significantly expands County leverage through collaboration with partner(s)

Positively impacts environment and/or climate change mitigation efforts

Considers equity meaningfully and comprehensively

n/a

Score         (-1,0,1,2)

6

2

2

1

2

2

1

0

16

Rationale

This project ties directly to HC Strategic Plan Objective R: Enhance disaster

This investment will maintain mission critical systems allowing continuous operations

Loss of critical systems would have a significant impact on Public Safety operations

Moderate direct/indirect benefit relative to costs

County has existing capability to implement, and dependencies are unlikely to impede

Better equipped to provide support to agencies throughout the county

Utilizing sustainable battery technology positively impacts climate mitigation

Meaningful and comprehensive equity

n/a