Title: Request for approval to execute an agreement with Cobb, Fendley & Associates, Inc. in the amount of $252,050.00 for Professional Engineering and related services to construct the Roadway Maintenance - Asphalt Rehabilitation Package - 1 - 2026, UPIN 25103MF3PJ01, Precinct 3, MWBE Contracted Goal: 9.07%, MWBE Current Participation: 11.20%.
Attachments: 1. 26-6287-Award-25103MF3PJ01-Asphalt Package 1-Cobb Fendley-P3-9.22.26.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: Commissioner, Precinct 3

Secondary Department Head/Elected Official: Commissioner Tom S. Ramsey, P.E.

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN - 25103MF3PJ01

Vendor/Entity Legal Name (if applicable): Cobb, Fendley & Associates, Inc.

 

MWBE Contracted Goal (if applicable): 9.07%

MWBE Current Participation (if applicable): 11.20%

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Cobb, Fendley & Associates, Inc. in the amount of $252,050.00 for Professional Engineering and related services to construct the Roadway Maintenance - Asphalt Rehabilitation Package - 1 - 2026, UPIN 25103MF3PJ01, Precinct 3, MWBE Contracted Goal: 9.07%, MWBE Current Participation: 11.20%.

end

 

Background and Discussion:

The project limits extend along Spring Cypress Road from approximately 500 feet east of T.C. Jester Boulevard to roughly 675 feet east of Holzworth Road, covering a total length of 5.6 miles.

The proposed improvements include base repairs, milling and overlay, updated pavement markings, and replacement of ADA ramps.

 

Expected Impact:

This project is intended to improve pavement condition, enhance roadway safety, and extend the service life of Spring Cypress Road. No impact on project schedule or cost is anticipated.

 

Alternative Options:

The County could elect to approve the requested task or choose to reject it. However, if not approved, the project will not proceed with construction.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

 3/27/2025

82, File #: 25-1722

PROFESSIONAL SERVICES AGREEMENT

 

 

 

 

Location:

Address (if applicable): Spring Cypress Rd

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper 3109

$

$252,050.00

$252,050.00

$252,050.00

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$252,050.00

$252,050.00

$252,050.00

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$252,050.00

$252,050.00

$252,050.00

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 9/17/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief, Engineering & Architectural Services, OCE

 

Attachments (if applicable): Contract & Exhibits