Legislation Details

File #: 24-3632    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/11/2024 In control: Commissioners Court
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Request for approval of a change in contract with Hayden Paving, Inc., in connection with final construction of Roadway - Crenshaw Road from South Shaver to Allen Genoa Road Reconstruction, adding eight calendar days, with an addition in the amount of $296,158.00, Job No. 20/0027-3, UPIN 22102MF2EE01, Precinct 2, MWDBE Contracted Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 20/0027, UPIN 22102MF2EE01

Vendor/Entity Legal Name (if applicable): Hayden Paving, Inc.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Hayden Paving, Inc., in connection with final construction of Roadway - Crenshaw Road from South Shaver to Allen Genoa Road Reconstruction, adding eight calendar days, with an addition in the amount of $296,158.00, Job No. 20/0027-3, UPIN 22102MF2EE01, Precinct 2, MWDBE Contracted Goal: N/A - project was awarded prior to launch of County’s M/WBE Program.

end

 

Background and Discussion:

This project includes the mill and overlay of Crenshaw Road from South Shaver to Allen Genoa Road.

The existing condition of the driveways that connected to the road is cracked and damaged, therefore, Precinct 2 representative recommended to mill and overlay all the driveways.

 

Expected Impact:

Contract time will be increased.

 

Alternative Options:

Maintain the original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

x Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/07/2020

16.d.8.d

Contract Award

08/08/2023

23-4425

Contract Amendment for additional funds and extension of project term

11/14/2023

23-6817

Contract Amendment for additional funds and extension of project term

 

 

 

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other Fund 3021

$

$296,158.00

$296,158.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$296,158.00

$296,158.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$296,158.00

$296,158.00

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: June 25, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B