Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 21090MF22H01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable):N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable):N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement (SOLS) with CenterPoint Energy to install eight (8) braces on the primary poles, in multiple locations, in connection with Humble Road Place and Parkland Estates Subdivisions Drainage Improvements - 2018, UPIN 21090MF22H01, Precincts 1 and 2.
end
Background and Discussion:
The project includes Drainage and Infrastructure Improvements for and related to Humble Road Place and Parkland Estates Subdivisions. The work includes base repairs, mill and overlays, ditch regrading, culvert replacements, and adjustments around eight (8) poles in different location which are in the Harris County ROW. CenterPoint Energy to install Brace, for the eight (8) poles, and remove all braces after conclusion of the project.
Expected Impact:
This action allows the continuation of the contracted work.
Alternative Options:
If no action is taken, the project may experience construction delays.
County Strategic Plan Goal: 1. Make Harris County safer and more just.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H6: Expand neighborhood drainage programs.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan:
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
|
|
|
Location:
Address (if applicable):
Precinct(s): Choose an item.
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$ |
$ |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 5/22/2025
Anticipated Implementation Date (if different from Court date): 5/30/2025
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer
Attachments (if applicable): Pole Brace - CNP Elec - COMBINED SKETCH