Legislation Details

File #: 25-0594    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 1/10/2025 In control: Commissioners Court
On agenda: 1/23/2025 Final action: 1/23/2025
Title: Request for approval to execute an agreement with Binkley & Barfield, Inc in the amount of $171,910.00 for Construction Phase Services in connection with Dowdell Woods Subdivision Drainage Improvements, UPIN 19103MF14A01, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
Attachments: 1. 25-0594-Award-UPIN 19103MF14A01-CPS-Dowdell Woods-Binkley & Barfield-P3

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 19103MF14A01

Vendor/Entity Legal Name (if applicable): Binkley & Barfield, Inc

 

MWBE Contracted Goal (if applicable): 0%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  0% - Non-Divisible

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Binkley & Barfield, Inc in the amount of $171,910.00 for Construction Phase Services in connection with Dowdell Woods Subdivision Drainage Improvements, UPIN 19103MF14A01, Precinct 3, Justification for 0% MWBE Participation Goal:  0% - Non-Divisible.

end

 

Background and Discussion:

The project is located in Northwest Harris County in both the White Oak Bayou and Cypress Creek watersheds, west of North Eldridge Parkway and north of Cypress North Houston Road. The existing drainage system consists of roadside ditches. Proposed improvements include an upgraded storm sewer system and re-grade roadside ditches. This agreement will provide Professional Services from the Engineer of Record during construction phase.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Dowdell Woods community. No impact on project schedule or cost anticipated.

 

Alternative Options:

If no action is taken, the engineer of record will not be accessible for support through the construction of the project.

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/10/2019

2(1.J.2)

Study Report Approval by Costello

09/24/2019

8(1.d.8)

Authorization to Negotiate for Engineering Services

02/11/2020

2(1.g.2)

Contract Award for Professional Engineering Services

08/10/2021

99(21-3988)

Amend Contract Award for Professional Engineering Services

09/13/2022

 

Study Report Approval

 

 

 

 

Location: Dowdell Woods Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109

$

$ 171,910.00

$ 171,910.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$ 171,910.00

$ 171,910.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$ 171,910.00

$ 171,910.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/23/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Office of the County Engineer

 

Attachments (if applicable): Construction Phase Services Agreement