Legislation Details

File #: 26-5943    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/2/2026 In control: Commissioners Court
On agenda: 9/17/2026 Final action:
Title: Request for approval of a change in contract with Statewide Traffic Signal Company, in connection with final construction of Intersection Improvements - Hufsmith Rd at FM 2978, Stuebner Airline Rd, & Kuykendahl Rd-PhaseII-2024, adding 60 calendar days, with a deduction in the amount of $126,493.80, Job No. 23/0341-1, UPIN 24103MF34P02, Precinct 3, MWBE Contracted Goal: 8.60%, MWBE Current Participation: 11.74%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official:

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0341, UPIN 24103MF34P02

Vendor/Entity Legal Name (if applicable): Statewide Traffic Signal Company

 

MWBE Contracted Goal (if applicable): 8.60%

MWBE Current Participation (if applicable): 11.74%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Statewide Traffic Signal Company, in connection with final construction of Intersection Improvements - Hufsmith Rd at FM 2978, Stuebner Airline Rd, & Kuykendahl Rd-PhaseII-2024, adding 60 calendar days, with a deduction in the amount of $126,493.80, Job No. 23/0341-1, UPIN 24103MF34P02, Precinct 3, MWBE Contracted Goal: 8.60%, MWBE Current Participation: 11.74%.

end

 

Background and Discussion:

This On-Call project involves modifying an existing traffic signal located at the intersection of Kuykendahl Rd. and Hufsmith.  This On-Call project consisted of the modification of an existing traffic signal system with appropriate pedestrian facilities that includes upgrades to ADA ramps, converting eastbound lanes to dedicated left, shared thru-left, and dedicated right turn lane with 150 ft storage; provide a dedicated southbound right turn lane with 200 ft storage; striping, signage improvements at the intersection of Kuykendahl Rd and Hufsmith, Precinct 3.  This project was completed to enhance and provide a reliable and safe route of transportation to the residents of Harris County at the existing intersection.  The project was overseen by Harris County Engineering Department CPD-team.

Final Adjustments ($0)

 

Change included additional funds for the following:

PCO- 3- Grant 60 additional days due to delay waiting for Roadwork and Drainage completion.

 

Expected Impact:

The traffic signal rebuild will improve the safety and efficiency of both pedestrian and vehicular traffic

 

Alternative Options:

No alternative option, otherwise, Contractor will be delay for payment of his final pay estimate, which include the retainage.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  G1: Expand pedestrian and cyclist infrastructure on County-managed roads,

Economy Initiative (Goal 3): J2: Increase the strength and size of MWBE prime vendors.

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/30/2024

316 (24-0571)

Contract Award

01/23/2025

255 (25-0681)

Contract Renewal

 

Location:

Address (if applicable): Kuykendahl Rd and Hufsmith

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

-$126,493.80

-$126,493.80

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$126,493.80

-$126,493.80

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$-$126,493.80

-$126,493.80

 

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 9/17/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form1258B