File #: 26-4396    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 6/25/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval of an agreement with Carollo Engineers, Inc., in the amount of $1,615,237.80, to provide design and construction phase services of the Goose Creek Channel Conveyance Improvements and Rollingbrook Stormwater Detention Basin and preliminary engineering for the Northern Segment-Stage 1 (Goose Creek Watershed, Bond ID F-120, Project ID O100-00-00-E003, Agreement No. 2026-11, Precinct 2, MWBE Contracted Goal: 19.60%, MWBE Current Participation: 24.73%).

Primary Department: Flood Control District

Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM, Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): O100-00-00-E003

Vendor/Entity Legal Name (if applicable): Carollo Engineers, Inc.

 

MWBE Contracted Goal (if applicable): 19.60%

MWBE Current Participation (if applicable): 24.73%

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an agreement with Carollo Engineers, Inc., in the amount of $1,615,237.80, to provide design and construction phase services of the Goose Creek Channel Conveyance Improvements and Rollingbrook Stormwater Detention Basin and preliminary engineering for the Northern Segment-Stage 1 (Goose Creek Watershed, Bond ID F-120, Project ID O100-00-00-E003, Agreement No. 2026-11, Precinct 2, MWBE Contracted Goal: 19.60%, MWBE Current Participation: 24.73%).

end

 

Background and Discussion:

This Agreement provides design and construction-phase services for the Goose Creek Channel Conveyance Improvements and the Rollingbrook Stormwater Detention Basin (Southern Segment), as well as a Preliminary Engineering Analysis for the Northern Segment (Stage 1). For the Southern Segment, the scope includes improving channel conveyance capacity, designing a stormwater detention basin (SWDB) to reduce flooding, addressing encroachments, and relocating the existing waterline. For the Northern Segment, the scope includes a two-stage analysis to evaluate hydraulic benefits, determine detention volume needs, assess alternative site locations, and develop conceptual high-level engineering deliverables.

 

Expected Impact:

The project seeks to reduce flood risks and strengthen resiliency in the Goose Creek watershed by providing up to 230 ac-ft of detention along O100-00-00, and remove 112 structures, 28 acres of inundation area, and 1.4 miles of roadway from flooding during the 100-year event.

Alternative Options:

The alternative to approving this item would be to select another firm for the project, which would result in delay in project completion.

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

05/11/2021

101.

ATN

08/14/2021

110.

Agreement

 

Location: N/A

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

4.a.3 - Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$1,615,237.80

$1,615,237.80

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$1,615,237.80

$1,615,237.80

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$1,615,237.80

$1,615,237.80

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 7/9/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Agreement and Map