Legislation Details

File #: 24-3596    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/10/2024 In control: Commissioners Court
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Request for approval to execute an amendment with Walter P. Moore & Associates, Inc. in the amount of $119,400 for Professional Engineering Services in connection with pedestrian and bicycle bridge over White Oak Bayou at De Soto Street, UPIN 19101MF0XW01, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN 19101MF0XW01

Vendor/Entity Legal Name (if applicable): Walter P. Moore & Associates, Inc.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval to execute an amendment with Walter P. Moore & Associates, Inc. in the amount of $119,400 for Professional Engineering Services in connection with pedestrian and bicycle bridge over White Oak Bayou at De Soto Street, UPIN 19101MF0XW01, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

Background and Discussion:

The project was initiated in 2019 to design and construct a pedestrian and bike bridge to provide the connection between Oakbrook Greenspace and De Soto Street at White Oak Bayou. Harris County will design and construct the bridge. City of Houston will take ownership of asset and maintenance after warranty period.

 

Expected Impact:

The amendment is needed to address U.S. Army Corps of Engineers 408 permit as well as landscape requirement.

 

Alternative Options:

No alternative options. Project will be delayed or cancelled.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X_ Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

03/27/18

1.e.8

Authorization to Negotiate

10/13/20

1.g.2

Consultant Agreement

 

Location: White Oak Bayou at De Soto St

Address (if applicable): N/A

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$119,400.00

$119,400.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$119,400.00

$119,400.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$119,400.00

$119,400.00

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: June 25, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department:  Erwin Burden, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Amendment Agreement