File #: 25-0453    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/8/2025 In control: Commissioners Court
On agenda: 1/23/2025 Final action: 1/23/2025
Title: Request for approval of an amendment to an agreement with Midtown Engineers, LLC, in the amount of $428,473, to provide additional design, bidding, and construction phase engineering services in support of two detention basins along Cypress Creek at Kuykendahl Road and IH-45, HCFCD Unit K500-31-00 (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-G002, Agreement No. 2020-09, Precincts 1 and 3, MWBE Contracted Goal: 19%).
Attachments: 1. 012325 AGMT MIDTOWN 2020-09 PCT 1 AND 3 backup.pdf

Primary Department: Flood Control District

Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): K100-00-00-G002

Vendor/Entity Legal Name (if applicable): Midtown Engineers, LLC

 

MWBE Contracted Goal (if applicable): 19%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with Midtown Engineers, LLC, in the amount of $428,473, to provide additional design, bidding, and construction phase engineering services in support of two detention basins along Cypress Creek at Kuykendahl Road and IH-45, HCFCD Unit K500-31-00 (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-G002, Agreement No. 2020-09, Precincts 1 and 3, MWBE Contracted Goal: 19%).

end

 

Background and Discussion:

This Amendment No. 2 will provide additional design, bidding, and construction phase services (CPS) in support Cypress Creek Batch 5 stormwater detention basin and channel maintenance projects. This agreement provides engineering support to the major Cypress Creek channel maintenance repairs, which were separated into five (5) Batch packages under the Bond Program. 

 

Expected Impact:

This amendment will allow the Flood Control District to provide professional engineering and related services as may be needed for this project located within Harris County, Texas. 

 

Alternative Options:

The alternative to approving this item would be procuring another consultant to complete the work, which would result in design and construction delays in the CDBG projects and the work order projects.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

03/26/2019

2.c.4

ATN

05/14/2019

2.a.12

Agreement

01/09/2024

74.

Amendment

 

Location: N/A

Address (if applicable):

Precinct(s): Precincts 1 & 3

 

Fiscal and Personnel Summary

Service Name

4.a.3 - Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$50,000

$50,000

$50,000

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$50,000

$50,000

$50,000

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$50,000

$50,000

$50,000

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/23/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Agreement and Map