Legislation Details

File #: 24-0664    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 1/23/2024 In control: Commissioners Court
On agenda: 1/30/2024 Final action: 1/30/2024
Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Main Lane Industries, LTD in connection with Subdivision Roadway Asphalt Rehabilitation - Hemwick, Job No. 22/0121, UPIN 21103N303703, Precinct 3.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

 

Project ID (if applicable): Job No. 22/0121

Vendor/Entity Legal Name (if applicable): Main Lane Industries, LTD

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Transmittal by the Office of the County Engineer of a substantial completion certificate with Main Lane Industries, LTD in connection with Subdivision Roadway Asphalt Rehabilitation - Hemwick, Job No. 22/0121, UPIN 21103N303703, Precinct 3.

end

 

Background and Discussion:

 

The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer.  Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset.  The establishment and reporting of this date is important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001.  These certificates provide a method by which Harris County may document and record this date.

 

Expected Impact:

 

This action establishes the date on which a capital improvement enters service as a Harris County asset.

 

Alternative Options:

 

No alternative option

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/10/2021

382

Contract Award

06/06/2023

39

Contract Amendment for additional funds

12/05/2023

37

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 30, 2024

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Dr. Hatem Elbastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department

Attachments (if applicable): Substantial Completion Form