Legislation Details

File #: 26-7876    Version: 1 Name:
Type: Investment Memo Status: Agenda Ready
File created: 11/16/2026 In control: Commissioners Court
On agenda: 12/3/2026 Final action:
Title: Request for approval of a Final Investment Memo for the Precinct 2-PW Equipment Acquisition project, for an amount of $1,250,000, and request for approval of commercial paper funding in the amount of $1,250,000.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Commissioner, Precinct 2
Primary Department Head/Elected Official: Adrian Garcia, Commissioner

Managing Department: Commissioner, Precinct 2
Managing Department Head/Elected Official: Adrian Garcia, Commissioner

Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo

Project Name: Precinct 2 FY27-PW Equipment Acquisition
Project ID (if applicable): 100001000001720
Vendor Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $1,250,000
Total Estimated Project Cost: $1,250,000

Request Summary:
title
Request for approval of a Final Investment Memo for the Precinct 2-PW Equipment Acquisition project, for an amount of $1,250,000, and request for approval of commercial paper funding in the amount of $1,250,000.
end

Project Description:
This project supports the acquisition of essential vehicles and equipment to strengthen the department’s operational effectiveness and service delivery. These assets are critical for maintaining infrastructure, roadways, supporting daily operations, improving constituent access to well-maintained public areas, and advancing health, safety, wellness, and overall responsiveness.
The requested investment will facilitate the timely and efficient completion of the procurement process, ensuring the department has the necessary resources to meet operational demands and continue providing essential services to the community.

Anticipated Project Expenditures and Timeline:
Project Scope Breakdown
Quantity
Estimated Cost
Estimated Total Cost
Estimated Completion

Zero Turn Mower – 60”

12

$18,000

$216,000
Q2-FY...

Click here for full text