Legislation Details

File #: 26-7875    Version: 1 Name:
Type: Investment Memo Status: Agenda Ready
File created: 11/16/2026 In control: Commissioners Court
On agenda: 12/3/2026 Final action:
Title: Request for approval of the Final Investment Memo for FY27 Precinct 2 Aging Operations Fleet and Equipment Upgrade project, for an amount of $1,250,000, and request for approval of commercial paper funding in the amount of $1,250,000.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Commissioner, Precinct 2
Primary Department Head/Elected Official: Adrian Garcia, Commissioner

Managing Department: Commissioner, Precinct 2
Managing Department Head/Elected Official: Adrian Garcia, Commissioner

Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo

Project Name: FY27 Precinct 2 Aging Operations Fleet and Equipment Upgrade
Project ID (if applicable): TBD
Vendor Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $1,250,000
Total Estimated Project Cost: $1,250,000

Request Summary:
title
Request for approval of the Final Investment Memo for FY27 Precinct 2 Aging Operations Fleet and Equipment Upgrade project, for an amount of $1,250,000, and request for approval of commercial paper funding in the amount of $1,250,000.
end

Project Description:
This project focuses on replacing aging and outdated equipment while strategically investing in new equipment to enhance operational efficiency, productivity, and service delivery across the Precinct. The project supports long-term operational sustainability while maximizing departmental resources and improving service to residents.
Anticipated Project Expenditures and Timeline:
Project Scope Breakdown
Estimated Cost
Estimated Completion

Equipment Replacement & Upgrades:
Parks Maintenance, Groundskeeping, Operations Assets
EV UTV (4)
Utility Tractor (3)
Gooseneck Heavy Duty Equipment Trailer (4)
Landscape Trailer (4)
Tractor Loader Backhoe (2)
Towable Wood Chipper (1)
Portable Generator (5)
Zero-turn Riding Lawn Mower (1)
Chipper Truck (1)
Ford Explorer (1)
Restroom Trailer (1)
EV UTV (2)
Replace...