Legislation Details

File #: 26-7852    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 11/13/2026 In control: Commissioners Court
On agenda: 12/3/2026 Final action:
Title: Request for approval of a change in contract No. 4 with Express Dump Truck Service of Houston LLC, for general repairs, adding 70 calendar days and resulting in an addition of $146,159.42 to the contract amount (Halls Bayou Watershed, Project ID P118-32-01-X003, Job No. 24/0428, Precinct 2, MWBE Contracted Goal: 19.80, MWBE Current Participation: 9.31%).
Attachments: 1. 120326 CIC 4 EXPRESS DUMP P118-32-01-X003 PCT 2 backup .pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM, Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): P118-32-01-X003
Vendor/Entity Legal Name (if applicable): Express Dump Truck Service of Houston LLC

MWBE Contracted Goal (if applicable): 19.80%
MWBE Current Participation (if applicable): 9.31%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract No. 4 with Express Dump Truck Service of Houston LLC, for general repairs, adding 70 calendar days and resulting in an addition of $146,159.42 to the contract amount (Halls Bayou Watershed, Project ID P118-32-01-X003, Job No. 24/0428, Precinct 2, MWBE Contracted Goal: 19.80, MWBE Current Participation: 9.31%).
end

Background and Discussion:
This change in contract is needed to complete the construction contract for this project. The change in contract is needed to add a new project site to the project to meet the state statute for a public construction project to meet at least 82% of the original purchase. At project substantial completion only 61% of the total cost was utilized. The purpose of this contract change is to add a new project site to comply with state statute for minimum work completed. The contract change includes adding a new site for clearing and grubbing activities. The net change in value to this contract is 25% to the purchase order and 73% to the contract duration. The funding source is O&M.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduc...

Click here for full text