Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM, Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): Z100-00-00-P044
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an escrow agreement with JP Morgan Chase Bank, N.A., in connection with the Texas Water Development Board grant for the SAFER Study, to deposit funds for the payment of sums due by the Flood Control District (Bond ID Z-08, Project ID Z100-00-00-P044, Agreement No. 2026-124, Countywide).
end
Background and Discussion:
This request is for approval of an escrow agreement with JP Morgan Chase Bank for the Texas Water Development Board FIF grant for the SAFER Study (Z100-00-00-P044) for the deposit of funds for the payment of sums due by the Flood Control District.
Expected Impact:
This agreement will provide funding assistance for the SAFER Study. The Flood Control District will utilize its resources and applicable consultants during the project, as well as the management of the grant approval process in compliance with Harris County statutes, applicable laws of the state of Texas, and policy regarding state grant awards.
Alternative Options:
The alternative to approving this item would be to not utilize these State Community Directed Funding allocation, which would result in need for a different funding source to pay for this project.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitabl...