Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM, Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Grant - Amendment
Project ID (if applicable): D111-00-00-C002
Vendor/Entity Legal Name (if applicable): Texas Division of Emergency Management
MWBE Contracted Goal (if applicable):
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): 0%
Justification for 0% Grant Indirect Costs Rate (if applicable): HCFCD, HCTRA, HHS
Request Summary (Agenda Caption):
title
Request by the Flood Control District for approval to accept an amendment to an agreement with the Texas Division of Emergency Management to extend the grant end date to April 1, 2028, for the FEMA Pre-Disaster Mitigation grant (Brays Bayou Watershed, Bond ID C-12, Project ID D111-00-00-C002, Precinct 1).
end
Background and Discussion:
This grant award amendment will continue to provide financial and technical assistance to the Flood Control District for structural reconstruction of Poor Farm Ditch (Project ID D111-00-00), a tributary to Brays Bayou, to replace the deteriorated concrete channel and restore design capacity to reduce flood risk for adjacent communities. The project includes completion of final design, bidding, and construction of approximately 3,100 linear feet of new channel within existing HCFCD right-of-way, delivered in coordination with the Cities of Southside Place, West University Place, and the City of Houston. The amendment extends the period of performance to April 1, 2028.
Expected Impact:
This grant amendment will allow the Flood Control District to continue progress on the Poor Farm Ditch Improvement Project by extending the period of performance with no change in funding. The additional time wi...
Click here for full text