Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: Choose an item.
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 260251
Vendor/Entity Legal Name (if applicable): Hassell Construction Group, LLC
MWBE Contracted Goal (if applicable): 30.00%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to Hassell Construction Group, LLC in the amount of $3,668,105 for extension of Birnam Wood Boulevard from Hickorygate Drive to south of Harris County Flood Control District (HCFCD) Unit # J109-01-01 for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (260251), MWBE Contracted Goal: 30.00%.
end
Background and Discussion:
Based on the bid results, the recommendation of OCE and the design consultant, MBCO Engineering, LLC, it is recommended that the lowest responsive bidder, Hassell Construction Group, LLC be awarded the construction contract to perform the work for Extension of Birnam Wood Boulevard from Hickorygate Drive to south of Harris County Flood Control District (HCFCD) Unit # J109-01-01 for Harris County Precinct 3.
Expected Impact:
Awarding the contract will allow the recommended bidder to proceed with the extension of Birnam Wood Boulevard from Hickorygate Drive to south of Harris County Flood Control District (HCFCD) Unit # J109-01-01.
Alternative Options:
The alternative is not to award the contract. If no action is taken, Birnam Wood Boulevard from Hickorygate Drive to south of Harris County Flood Control District (HCFCD) Unit # J109-01-...