Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Commissioner Rodney Ellis
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 20104MF1BJ01
Vendor/Entity Legal Name (if applicable): Northwest Harris County Municipal Utility District 6
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Northwest Harris County Municipal Utility District No. 6 to relocate their waterline and force main facilities and related appurtenances for improvements to Bourgeois Road from Cutten Road to West Richey Road, UPIN 20104MF1BJ01, Precinct 1.
end
Background and Discussion:
The project is located in northwest Harris County, north of Sam Houston Tollway, south of FM 1960, and east of SH 249. The project area consists of residential homes, elementary school, and industrial warehouses. Existing Bourgeois Road is a two-lane undivided asphalt roadway with drainage ditches on both sides. The proposed improvements will add raised medians and turn lanes with a curb and gutter pavement section. Sidewalks are proposed on both sides of the roadway.
Expected Impact:
The interlocal agreement will allow Harris County to relocate Northwest Harris County Municipal Utility District 6 waterline and force main facilities in conflict with improvements to Bourgeois Road project.
Alternative Options:
Northwest Harris County Municipal Utility District 6 can independently design and relocate waterline and ...